Complete project overview

RERA Telangana · Registration filing
Units
10 units
Unit mix
5 × 3BHK, 5 × 2BHK
Saleable area
72–126 sq mper unit, as filed
Floors
5
Land area
397 sq m
Built-up area
1,170 sq m

Timeline

RERA approvedFeb 2022
Proposed completionJan 2028
TodayJul 2026
Construction progress

55% overall, as filed

Podiums0%
External finishes0%
OC-readiness0%
Flat fit-out40%
Internal finishes50%
Stairs & lifts60%
Excavation100%
Basement & plinth100%
Stilt floor100%
Superstructure100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

10 of 10 available
BuildingFloorTypeArea sq mAvailable
GRC RESIDENCY13BHK1261 of 1
GRC RESIDENCY12BHK721 of 1
GRC RESIDENCY23BHKmortgaged1261 of 1
GRC RESIDENCY22BHK721 of 1
GRC RESIDENCY33BHK1261 of 1
GRC RESIDENCY32BHK721 of 1
GRC RESIDENCY43BHK1261 of 1
GRC RESIDENCY42BHK721 of 1
GRC RESIDENCY53BHK1261 of 1
GRC RESIDENCY52BHK721 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

JP INFRA

PartnershipPromoter type
Karimnagar, TelanganaBased in
3Projects
1City
2022–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
85 homeson the public record across 3 projects
10,317 sq mbuilt-up filed
3,299 sq mland declared
₹12.70 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Directorate of Town & Country Planning (DTCP)Town & Country Planning (DTCP)this project2 of 3 projects
Commissioner, APCRDAMunicipal / Corporation1 of 3 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
Vidya Nagar(Part)_W49
District
Karimnagar
Pincode
505001
North boundary
VACANT LAND
East boundary
VACANT LAND
South boundary
9M ROAD
West boundary
VACANT LAND
What’s nearby
SchoolsNearest school 2.0km away
HealthcareHospital 674m away · Clinic within 2km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km · Mall 1.7km away
Getting around
Expressway 623 mPrimary road 1.2 kmRailway line 2.1 kmRailway station 3.1km away (Karimnagar)Bus stop within 1km
Water & environment
Water body 1.4 km
distances only — not a flood assessment
Declared external development
Roads0%
Water supply0%
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Directorate of Town & Country Planning (DTCP)

Town & Country Planning (DTCP)
Building Permit no. 3011/W49/2019/5779Survey no. 1275/1
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan 3011/W49/2019/5779 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

DTCP

Town & Country Planning · towns & district HQs across Telangana

Has approved 3,737 RERA projectsabout 1 in 3 in Telangana, more than any other body in the state.

a plotted-layout market32% apartments · 68% plotted layouts. Apartments like yours are the smaller share here — this body mostly approves plotted layouts.

Builders
2,933
On record
41,686 flats · 4,33,404 plots
Reach
287 mandals
Since
2012

More layout-heavy than Telangana overall — 68% plots here vs 34% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.