Complete project overview

RERA Telangana · Registration filing
Units
50 units
Unit mix
30 × 2BHK, 20 × 3BHK
Saleable area
96–132 sq mper unit, as filed
Floors
5
Land area
2,023 sq m
Built-up area
7,173 sq m

Timeline

RERA approvedApr 2023
Proposed completionMar 2026
TodayJul 2026
Construction progress

20% overall, as filed

Basement & plinth0%
Podiums0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Excavation100%
Stilt floor100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

50 of 50 available
BuildingFloorTypeArea sq mAvailable
GREEN FORT12BHK1091 of 1
GREEN FORT13BHKmortgaged1324 of 4
GREEN FORT12BHKmortgaged961 of 1
GREEN FORT12BHKmortgaged984 of 4
GREEN FORT22BHK961 of 1
GREEN FORT22BHK1091 of 1
GREEN FORT22BHK984 of 4
GREEN FORT23BHK1323 of 3
GREEN FORT23BHKmortgaged1321 of 1
GREEN FORT33BHK1324 of 4
GREEN FORT32BHK984 of 4
GREEN FORT32BHK1091 of 1
GREEN FORT32BHK961 of 1
GREEN FORT43BHK1324 of 4
GREEN FORT42BHK984 of 4
GREEN FORT42BHK961 of 1
GREEN FORT42BHK1091 of 1
GREEN FORT53BHK1324 of 4
GREEN FORT52BHK984 of 4
GREEN FORT52BHK961 of 1
GREEN FORT52BHK1091 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

SRI JAGAJJANANI INFRA PROJECTS PRIVATE LIMITED

CompanyPromoter type
Hyderabad, TelanganaBased in
2Projects
1City
2021–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
60 homeson the public record across 2 projects
9,712 sq mbuilt-up filed
2,771 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RERA Telangana · Registration filing
Locality
Abdullapurmet
Village
KUNTLOOR
Mandal
Abdullapurmet
District
Ranga Reddy
Pincode
501505
North boundary
Land Belongs to J Venkat Narsimha Reddy
East boundary
Land Belongs to Solipuram Sumathi Reddy
South boundary
267 Part
West boundary
30 Ft Wide Road
What’s nearby
SchoolsNearest school 2.0km away · College or university 366m away
HealthcareNearest hospital 2.7km away · Pharmacy within 500m
LifestylePark 1.3km away
ShoppingNo supermarket within 2km
Getting around
Expressway 2.0 km · Vijaywada HighwayNo metro or railway within 5kmBus stop within 500m
Water & environment
Water body 1.4 km · Kuntloor Cheruvu
distances only — not a flood assessment
Government land classification

Land here includes House Sites (residential), plus Dry land, Agricultural Land fit for H.S.. The state classes land per survey— confirm your plot’s survey number is House Sites.

Telangana Registration & Stamps
Declared external development
Roads0%
Water supply0%
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
Price analysisno declared cost on this filing — one government benchmark below

This state’s RERA filing carries no declared build cost at all — nothing to turn into a per-unit or per-sq-ft figure here. The one real, government-sourced number below is the closest thing to a benchmark this record can offer.

Government guidance value
₹1,200/sq ydHouse Sites

₹1,435/sq m · effective Jan 2013

The state’s minimum value for this village’s land, set for stamp duty — a floor, not a market price. Source: Telangana Registration & Stamps.

04

Planning authority

RERA Telangana · Approved building plan

Hyderabad Metropolitan Development Authority (HMDA)

Urban Development Authority
Building Permit
Survey no. Sy No 267 Part

The promised possession date (31 Mar 2026) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

HMDA

Urban Development Authority · Hyderabad metropolitan periphery

Has approved 3,643 RERA projectsabout 1 in 3 in Telangana.

an apartments market72% apartments · 28% plotted layouts. Apartments like yours are this body's core business.

Builders
2,462
On record
3,98,695 flats · 1,96,015 plots
Reach
71 mandals
Since
2016

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.