Complete project overview
RAJ-RERA · Registration filing- Land area
- 18,986 sq m
- Completion deadline extended
- 2 extensions on record — latest to 10 Oct 2021declared reason: force majeure
- Description
- This Project is approved under the CM Jan Avas Yojna-2015 in Provision 3B. This Project contains 102 LIG & 33 EWS UNITS (TOTAL 135 UNITS) and 7 vacant plots. So according to policy the completion date of Project is given 24 months from the date of approval of maps. It is also mention that time taken by any Govt. agency in issuing required Certificate / Approval will be deducted from the total construction period. Approval of this Project is issued on 11/10/2017, the estimated completion date of the Project is 10/10/2019. We have not appointed any contractor till date. but developer also reserve the right to appoint any contractor in future. We are develop and construct the project with our own source and supervision. We have provided 2 two-wheeler parking in LIG unit and 1 two-wheeler parking in EWS unit according to rules CM Jan Awas Yojana 2015 accordingly therefore total number of two-wheeler parking provided is 135 and visitor parking is 102.
Timeline
Builder’s track record
RAJ-RERA · Promoter registrationAnsita Infra Creations Private Limited
The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
Location & price analysis
RAJ-RERA · Registration filing- Address
- 2442, 2443, 2444, Alanpur, Sawai Madhopur, Sawai Madhopur, 322021
- Taluka
- Sawai Madhopur
- District
- Sawai Madhopur
- Pincode
- 322021
₹15.16 Cr declared. What that works out to:
This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.
Planning authority
RAJ-RERA · Approved building planThe promised possession date (10 Oct 2019) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.
A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.
Urban Improvement Trust
A city-level Urban Improvement Trust — Rajasthan's town-development body in cities without a development authority. It has approved 612 RERA projects across 20 districts — about 1 in 4 in Rajasthan.
Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.
What this record cannot tell you
- Build quality — no filing records how well it was actually built.
- Private disputes — only complaints escalated to the authority appear here.
- What it will be worth — the record is the past; it does not price the future.
- Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
- Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.