01

Complete project overview

RAJ-RERA · Registration filing
Plots
44 plots
Land area
12,650 sq m
Description
As per Township Policy 2010, 12.5% of Total Saleble Area I.E. 16,17,18,26,27,28 were mortgaged with nagarpalika nohar for internal development work. Open Area is 3755.35 sq mtr which comprises 3755.35 sq mtr for Road

Timeline

Construction startFeb 2026
RERA registeredApr 2026
Proposed completionAug 2027
TodayJul 2026

Find your plot

Filed by type and size, in the batches the promoter registered — not a per-plot listing. Look yours up.

44 plots across 12 batches
TypeArea sq mCount
Plot19512
Plot1953
Plot1932
Plot1901
Plot1824
Plot1693
Plot1691
Plot18112
Plot1812
Plot1561
Plot1792
Plot2491

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each size exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

RAJ-RERA · Promoter registration

SITA DEVI

IndividualPromoter type
Hanumangarh, RajasthanBased in
2Projects
1City
2026–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
64 plotson the public record across 2 projects
16,809 sq mplotted area
16,809 sq mland declared
₹1.20 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Nagar Palika, NoharMunicipal / Corporation1 of 2 projects
Senior Town PlannerTown & Country Planningthis project1 of 2 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
Paththar No. 301/438, Murbbba No.–52,Killa No. 3/1 (0.0250 Hect.), Killa No. 3/2 (0.2280Hect.), Killa No. 8 (0.2530 Hect.),Killa No. 13 (0.2530 Hect.),Killa No. 18 (0.2530 Hect.), Killa No. 23 (0.2530 Hect.)Total Area 1.2650 hectare, Chak 1 NHR’A’, Tehsil –Nohar, Dist. Hanumangarh, PIN- 335523, Rajasthan , Chak 1 NHR’A’, Nohar, Nohar, Hanumangarh, 335523
Village
Nohar
Taluka
Nohar
District
Hanumangarh
Pincode
335523
Price analysisdeclared build cost — not a sale price

₹65.00 Lakh declared to build 44 plots. What that works out to:

₹1.48 Lakhdeclared cost per plotall-in — land + construction
₹48/sq ftof plotted area₹514/sq m
54%of the cost is land₹26/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RAJ-RERA · Approved building plan

Senior Town Planner

Town & Country Planning
Layout Permitapproved 10 Feb 2026 · 5 mo ago
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Town Planning office

The state Senior Town Planner's office. It has approved 115 RERA projects across 18 districts about 1 in 19 in Rajasthan.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.