Complete project overview
RAJ-RERA · Registration filing- Units
- 1,084 units
- Mix
- 418 × LIG · 338 × LIG UNIT (2 BHK) · 126 × EWS · 126 × EWS UNIT (1 BHK) · 60 × LIG UNIT (3 BHK) · 3 × SHOP TYPE 4
- Carpet area
- 7–57 sq mper-type range, as filed
- Land area
- 9,927 sq m
- Completion deadline extended
- 2 extensions on record — latest to 31 Mar 2023declared reason: other than force majeure
- Description
- 1. As per UDH order dated 27/06/2017 affidavit for fire noc has been submitted to the appropriate authority. 2. As per UDH order dated 22/06/2017 environment noc would be obtained before applying completion certificate. 3. Airport NOC not applicable in our project Copy of Application for Fire NOC and Environmental NOC has been submitted to the RERA. As per applicant request application 06 commercial shops as per maps were not filed at the time of RERA Registration, now following 06 commercial shops have been updated under apartment type details after approval, updated on 20.11.2019.
Timeline
Find your flat
Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.
Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).
Builder’s track record
RAJ-RERA · Promoter registrationShivaay Affodable Homes
The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
Location & price analysis
RAJ-RERA · Registration filing- Address
- 616, 617, 618, 619, Narsinghpura, Narsinghpura, Sanganer, Jaipur, 302006
- Village
- Narsinghpura
- Taluka
- Sanganer
- District
- Jaipur
- Pincode
- 302006
₹41.50 Cr declared to build 1,084 flats. What that works out to:
This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.
Planning authority
RAJ-RERA · Approved building planThe promised possession date (31 Mar 2021) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.
A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.
What this record cannot tell you
- Build quality — no filing records how well it was actually built.
- Private disputes — only complaints escalated to the authority appear here.
- What it will be worth — the record is the past; it does not price the future.
- Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
- Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.