Complete project overview

RERA Telangana · Registration filing
Units
20 units
Unit mix
20 × 2BHK
Saleable area
95 sq mper unit, as filed
Floors
5
Land area
726 sq m
Built-up area
2,297 sq m

Timeline

RERA approvedNov 2025
Proposed completionNov 2028
TodayJul 2026
Construction progress

0% overall, as filed

Excavation0%
Basement & plinth0%
Podiums0%
Stilt floor0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

20 of 20 available
BuildingFloorTypeArea sq mAvailable
HARITHA NIVAS12BHK954 of 4
HARITHA NIVAS22BHK954 of 4
HARITHA NIVAS32BHK954 of 4
HARITHA NIVAS42BHK954 of 4
HARITHA NIVAS52BHKmortgaged953 of 3
HARITHA NIVAS52BHK951 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

SUDHEER KUMAR NALLAMOTHU

ProprietorshipPromoter type
Suryapet, TelanganaBased in
1Projects
1City
2025–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
MIRYALAGUDA MANDAL
Village
Chaitnya Nagar
Mandal
Miryalguda
District
Nalgonda
Pincode
508207
North boundary
10M WIDE MAIN ROAD
East boundary
10M WIDE MAIN ROAD
South boundary
10M WIDE MAIN ROAD
West boundary
VENDORS PLOT
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 795m away
LifestylePark 1.1km away
ShoppingNo supermarket within 2km
Getting around
Expressway 1.1 km · Narketpally - Addanki - Medarametla RoadRailway line 4.3 kmRailway station 4.5km away (Miryalaguda)Limited bus connectivity nearby
Water & environment
Water body 881 mCanal 4.0 km
distances only — not a flood assessment
Declared external development
Roads0%
Water supply0%
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Directorate of Town & Country Planning (DTCP)

Town & Country Planning (DTCP)
Building Permit no. 007423/MIRY/00014/SWBP/2025Survey no. 51
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan 007423/MIRY/00014/SWBP/2025 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

DTCP

Town & Country Planning · towns & district HQs across Telangana

Has approved 3,737 RERA projectsabout 1 in 3 in Telangana, more than any other body in the state.

a plotted-layout market32% apartments · 68% plotted layouts. Apartments like yours are the smaller share here — this body mostly approves plotted layouts.

Builders
2,933
On record
41,686 flats · 4,33,404 plots
Reach
287 mandals
Since
2012

More layout-heavy than Telangana overall — 68% plots here vs 34% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.