HARSHIT HARMONY EXTENSION

PCGRERA191225002013 · RERA Chhattisgarh · https://gethorizon.in/projects/harshit-harmony-extension-dharsiwa-6sc8ekpj

01

Complete project overview

RERA Chhattisgarh · Registration filing
Units
426 units
Quarterly reports
2 on filequarterly progress reports filed with RERA

Timeline

RERA registeredDec 2025
Proposed completionMar 2028
TodaySep 2026
Construction progress

8% overall, as filed

Water Supply0%
Community Buildings0%
Water Conservation Rain Water Harvesting0%
Street Lighting10%
Energy Maanagement10%
Security Service10%
Sewerage15%
Open Parking20%
Internal Roads And Footpaths25%
Storm Water Drains25%
Landscaping And Tree Planting40%
Boundary Wall45%
Place Of Worship100%
From the builder's latest quarterly progress report filed with RERA Chhattisgarh — % complete overall and per infrastructure work, as of that filing. A dated snapshot, not a live tracker.
02

Builder’s track record

RERA Chhattisgarh · Builder registration

Singhania buildcon private limited

CompanyPromoter type
14Projects
5Cities
2018–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
657 homes · 1,943 plotson the public record across 14 projects
₹347.28 Crdeclared build cost

Build cost is what the builder declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from Singhania buildcon private limited— the full portfolio →

03

Location & price analysis

RERA Chhattisgarh · Registration filing
District
Raipur
Tehsil
Dharsiwa
Address
VILLAGE-GUMA BANA,TEHSIL-DHARSIWA,DIST-RAIPUR C.G.
What’s nearby
SchoolsNo schools within 2km
HealthcareNo hospital within 5km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 2.9 kmNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
Water body 857 mRiver 861 m · Kharun River
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹11.91 Cr declared to build 426 flats. What that works out to:

₹2.80 Lakhdeclared cost per flatall-in — land + construction
50%of the cost is land

This is what the builder filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Government Guidance Rate

Chhattisgarh registration department

In Chhattisgarh it’s called the collector guideline rate.

No government guidance rate is shown for this project.

Chhattisgarh's government guidance rates aren't in Horizon's record yet.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

06

Other projects nearby

The register · within 25 km

158 residential projects still under way within 25 km. Step out ring by ring:

Of the 27 projects the radar draws within 6 km — every kind, every stage — 6 are residential projects still under way. This list keeps only those, and looks further out.

6 projects between 3 and 6 km — showing the nearest 6.

4.2 km awayGroup Housing

pmay of 696 dus at birgaon ,raipur

commissioner birgaon municipal corporation · Raipur

Dec 2022registered
Dec 2027target completion
Declared cost₹30.96 CrScale696 flatsAuthorityRERA Chhattisgarh
5.2 km awayMixed Development

v3 bAlaji green city, & balaji hights

v.s. infrastructure. · Raipur

Jul 2018registered
Dec 2026target completion
Declared cost₹23.83 CrScale136 flatsAuthorityRERA Chhattisgarh
5.4 km awayMixed Development

construction of residential cum commercial complex (s+6) at ring road no-02 tatibandh raipur

executive engineer, c.g. housing board, division-01, kabir nagar raipur · Raipur

Jul 2022registered
Mar 2027target completion
Declared cost₹13.57 CrScale68 flatsAuthorityRERA Chhattisgarh
5.4 km awayMixed Development

HARSHIT LANDMARK (PHASE-III, BLOCK -E & F)

Singhania buildcon private limited · Raipur

Jun 2018registered
Jan 2028target completion
Declared cost₹64.03 CrScale112 flatsAuthorityRERA Chhattisgarh
5.4 km awayMixed Development

HARSHIT LANDMARK (PHASE-IV, BLOCK-G)

Singhania buildcon private limited · Raipur

Jun 2018registered
Jan 2028target completion
Declared cost₹56.94 CrScale119 flatsAuthorityRERA Chhattisgarh
5.4 km awayGroup Housing

FOR THE CONSTRCUTION OF 22 NO INDIVIDUAL (3BHK) DUPLEX HOUSES I/C DEVLOPMENT AT PHASE 1 KABIR NAGAR

executive engineer, c.g. housing board, division-01, kabir nagar raipur · Raipur

Oct 2025registered
Dec 2029target completion
no escrow declaredDeclared cost₹10.90 CrScale22 flatsAuthorityRERA Chhattisgarh

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.