HORIZONMarkets
01

Complete project overview

RERA Telangana · Registration filing
Units
18 units
Unit mix
18 × Commercial
Saleable area
104–346 sq mper unit, as filed
Floors
5
Land area
1,350 sq m
Built-up area
3,661 sq m
Road widening
208 sq mland set aside for road widening

Timeline

RERA approvedApr 2017
Proposed completionApr 2023
TodayJul 2026
Construction progress

35% overall, as filed

Podiums0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Superstructure50%
Excavation100%
Basement & plinth100%
Stilt floor100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

18 of 18 available
BuildingFloorTypeArea sq mAvailable
HYDERBASTI SITE1Commercial1082 of 2
HYDERBASTI SITE1Commercial1201 of 1
HYDERBASTI SITE1Commercial1171 of 1
HYDERBASTI SITE1Commercial1181 of 1
HYDERBASTI SITE1Commercial1041 of 1
HYDERBASTI SITE2Commercial3461 of 1
HYDERBASTI SITE2Commercial1941 of 1
HYDERBASTI SITE2Commercial1961 of 1
HYDERBASTI SITE3Commercialmortgaged3461 of 1
HYDERBASTI SITE3Commercialmortgaged1941 of 1
HYDERBASTI SITE3Commercial1961 of 1
HYDERBASTI SITE4Commercial3461 of 1
HYDERBASTI SITE4Commercial1941 of 1
HYDERBASTI SITE4Commercial1961 of 1
HYDERBASTI SITE5Commercial3461 of 1
HYDERBASTI SITE5Commercial1941 of 1
HYDERBASTI SITE5Commercial1961 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

VASLOGISTRUCTURE CORPO

PartnershipPromoter type
Hyderabad, TelanganaBased in
2Projects
2Cities
2017–2023Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
58 homeson the public record across 2 projects
43,226 sq mbuilt-up filed
9,647 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Greater Hyderabad Municipal Corporation (GHMC)Municipal / Corporationthis project1 of 2 projects
Hyderabad Metropolitan Development Authority (HMDA)Urban Development Authority1 of 2 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
SEC BAD
Village
Second Bazar
Mandal
Secunderabad
District
Hyderabad
Pincode
500003
North boundary
30FT ROAD
East boundary
NEIGHOBORS PLOT
South boundary
TEMPLE PROPERTY
West boundary
40 FT ROAD
What’s nearby
Schools2 schools within 500m · 6 educational institutions within 1km · College or university 443m away
HealthcareHospital 198m away · 4 clinics within 1km · Pharmacy within 500m
LifestylePark 919m away · 62+ restaurants and cafes within 1km
ShoppingSupermarket 741m away · Mall 166m away · Convenience store within 500m
Getting around
Expressway 801 m · Mahatma Gandhi RoadPrimary road 132 m · Rashtrapati RoadRailway line 769 mMetro station 472m away (Parade Grounds (Blue Line))5 bus stops within 500m
Water & environment
Canal 1.4 km
distances only — not a flood assessment
Declared external development
Roads0%
Water supply0%
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Greater Hyderabad Municipal Corporation (GHMC)

Municipal / Corporation
Building Permit

The promised possession date (26 Apr 2023) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

GHMC

Municipal Corporation · Hyderabad city core

Has approved 3,102 RERA projectsabout 1 in 4 in Telangana.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,994
On record
2,20,211 flats · 3,387 plots
Reach
65 mandals
Since
2016

More apartment-heavy than Telangana overall — 99% apartments here vs 66% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.