Complete project overview

RERA Karnataka · Registration filing
Status
New Project Launch
Plots
50 plots
Land parcels
1 survey no

Timeline

Project startedJul 2023
RERA registeredJul 2023
Proposed completionJun 2026
TodayJul 2026
Construction progress

95% overall, as filed

Common areas94%
From the promoter's latest quarterly progress report filed with RERA Karnataka — % complete overall and by stage, as of that filing. A dated snapshot, not a live tracker.

Find your plot

Every plot the builder registered, with the carpet area they filed. Look yours up and check it against what you were shown.

UnitTypeTotal sq m
1Plot225.25
2Plot168.18
3Plot173.63
4Plot179.09
5Plot184.54
6Plot190.07
7Plot193.75
8Plot98.45
9Plot108.84
10Plot119.30
11Plot137.47
12Plot131.40
13Plot111.48
14Plot111.48
15Plot111.48
16Plot144.18
17Plot111.48
18Plot111.48
19Plot111.48
20Plot111.48
21Plot111.48
22Plot111.48
23Plot111.48
24Plot111.48
25Plot111.48
26Plot132.71
27Plot124.52
28Plot111.48
29Plot111.48
30Plot111.48
31Plot111.48
32Plot111.48
33Plot111.48
34Plot111.48
35Plot111.48
36Plot111.48
37Plot161.30
38Plot98.80
39Plot92.89
40Plot111.48
41Plot111.48
42Plot111.48
43Plot111.48
44Plot111.48
45Plot111.48
46Plot111.48
47Plot111.48
48Plot111.48
49Plot111.48
50Plot111.35

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion.

02

Builder’s track record

RERA Karnataka · Promoter registration

ICON HOMZ LLP

Partnership FirmPromoter type
Bengaluru UrbanBased in
1Projects
1City
2023–2026Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RERA Karnataka · Registration filing
Taluk
Anekal
District
Bengaluru Urban
Pincode
560105
Address
Sy.No.54, Kachanayakanahalli Village , Jigani Hobli , Anekal , Bengaluru Urban, Karnataka - 560105
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 1.8km away · Clinic within 2km
LifestylePark 1.9km away
ShoppingNo supermarket within 2km · Mall 1.3km away
Getting around
Expressway 1.6 kmRailway line 2.5 km · Bangalore-SalemMetro station 2.2km away (Delta Electronics Bommasandra)Limited bus connectivity nearby
Water & environment
Water body 1.0 km · Kachanayakanahalli lake
distances only — not a flood assessment
Land, title & encumbrance
LandJoint development (JDA) — built on the owner’s land by agreement
ConversionConverted to non-agricultural
LitigationDeclared free of litigation
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
Price analysisdeclared build cost — not a sale price

₹5.20 Cr declared to build 50 plots. What that works out to:

₹10.40 Lakhdeclared cost per plotall-in — land + construction
37%of the cost is land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RERA Karnataka · Approved building plan

BMRDA - Bangalore Metropolitan Region Development Authority

Urban Development Authority
approved 15 May 2023 · 3 yrs ago
Layout Permit no. APA:LAO/118/2022-23Survey no. 54

The promised possession date (30 Jun 2026) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan APA:LAO/118/2022-23 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

BMRDA

Urban Development Authority · Bangalore Metropolitan Region Development Authority

Has approved 550 RERA projectsabout 1 in 16 in Karnataka.

a mixed market46% apartments · 54% plotted layouts.

Builders
441
On record
16,246 flats · 16,792 plots
Reach
14 taluks
Since
2017

More layout-heavy than Karnataka overall — 54% plots here vs 38% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Complaints register

None on record with RERA Karnataka against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.