HORIZONMarkets
01

Complete project overview

RERA Assam · Registration filing
Registration category
ONGOINGnew vs ongoing at registration
Land area
2,292 sq m
Local land measure
1Bhigha, 3katha, 11.31lecha
RERA validity
15 Feb 2025
Completion
Occupancy / Completion Certificate on record

Timeline

RERA registeredFeb 2021
Proposed completionApr 2023
TodayJul 2026
02

Builder’s track record

RERA Assam · Promoter registration

M/S INPERIAL REALTORS

Firm/ Proprietorship FirmPromoter type
1Projects
1City
2021–2023Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Assam · Registration filing
District
KAMRUP METRO
Mouza / circle
DISPUR
Town / village
Guwahati
Landmark
Rajdhani masjid
Site address
LAKHIMINAGAR, BYLANE 19, VILL. JATIA
Pincode
781019
What’s nearby
Schools3 schools within 1km · 6 educational institutions within 1km · College or university 484m away
HealthcareHospital 764m away · 8 clinics within 1km · Pharmacy within 1km
LifestylePark 1.7km away · Gym or sports centre 761m away · 17+ restaurants and cafes within 1km
ShoppingSupermarket 1.0km away · Mall 1.8km away · Bank 782m away
Getting around
Expressway 2.9 kmPrimary road 1.3 kmRailway line 4.8 kmNo metro or railway within 5kmBus stop within 1km
Water & environment
Water body 1.3 km
distances only — not a flood assessment
04

Planning authority

RERA Assam · Approved building plan

Guwahati Municipal Corporation

Municipal Corporation
Building Permitapproved 7 Feb 2022 · 4 yrs ago

The promised possession date (1 Apr 2023) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

Occupancy Certificate — the occupancy sign-off, on record

An Occupancy / Completion Certificateis on this project’s RERA Assam record — the completion / legal-to-occupy sign-off that most RERA records simply don’t carry. It is issued by the planning authority, not by RERA. Still confirm it covers your specific unit and block before you rely on it.

The approving body, at scale

Guwahati Municipal Corporation

Municipal corporation / board

Has approved 604 RERA projectsabout 1 in 1 in Assam, more than any other body in the state.

an apartments market98% apartments · 2% plotted layouts. Apartments like yours are this body's core business.

Builders
488
On record
45,695 flats · 10,758 plots
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Assam does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Assam does not publish a complaints register. This read cannot speak to them either way.