Complete project overview
RAJ-RERA · Registration filing- Land area
- 23,305 sq m
- Description
- Project brief: Mall cum Multiplex with 2 basements, retail on 4 floors (Lower ground to Second floor) and offices on 5 floors (Third to seventh floor). Multiplex (4 screens) at two levels. Further, due to document upload limitation we have uploaded approved building sanction plan drawings in following two sections (1st is in Building tab serial no. 2 in BUILDING DOCUMENTS and 2nd is in documents tab serial no. 2 in PROJECT RELATED APPROVAL DOCUMENT. Further, in Tab COMMON AREA-parking detail, we have mentioned parking number for visitor as 0 because as per our approved building plan drawing, dedicated parking number for visitor is not mentioned
Timeline
Builder’s track record
RAJ-RERA · Promoter registrationSepset Real Estate Limited
The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
Location & price analysis
RAJ-RERA · Registration filing- Address
- Vijay Raje Nagar Scheme, Pali Road, NH-65, District Jodhpur, Rajasthan-342005, Vijaya Raje Nagar, Pali Road, NH65 , District Jodhpur, Jodhpur, Jodhpur, 342005
- Village
- District Jodhpur
- Taluka
- Jodhpur
- District
- Jodhpur
- Pincode
- 342005
₹143.72 Cr declared. What that works out to:
This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.
Planning authority
RAJ-RERA · Approved building planThe promised possession date (30 Aug 2018) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.
A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.
What this record cannot tell you
- Build quality — no filing records how well it was actually built.
- Private disputes — only complaints escalated to the authority appear here.
- What it will be worth — the record is the past; it does not price the future.
- Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
- Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.