Complete project overview
RERA Assam · Registration filing- Registration category
- NEWnew vs ongoing at registration
- Plots
- 11 plots
- Land area
- 16,728 sq m
- Local land measure
- 12BIGHA-2KATHA-10LECHA
- RERA validity
- 30 Nov 2023
- Completion
- Occupancy / Completion Certificate on record
Timeline
Builder’s track record
RERA Assam · Promoter registrationM/S TRANSCENDENT CONDOMINIUMS PRIVATE LIMITED
The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
Location
RERA Assam · Registration filing- District
- KAMRUP METRO
- Mouza / circle
- GUWAHATI
- Town / village
- GUWAHATI
- Site address
- KRISHNA NAGAR COLONY, LAL GANESH, KALAPAHAR
- Pincode
- 781034
Planning authority
RERA Assam · Approved building planThe promised possession date (20 Nov 2023) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.
An Occupancy / Completion Certificateis on this project’s RERA Assam record — the completion / legal-to-occupy sign-off that most RERA records simply don’t carry. It is issued by the planning authority, not by RERA. Still confirm it covers your specific unit and block before you rely on it.
Guwahati Metropolitan Development Authority
Development authorityHas approved 122 RERA projects — about 1 in 7 in Assam.
an apartments market — 94% apartments · 6% plotted layouts. Layouts like yours are the smaller share here — this body mostly approves apartments.
- Builders
- 112
- On record
- 11,753 flats · 2,242 plots
- Reach
- 2 districts
- Since
- 2010
Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.
What this record cannot tell you
- Build quality — no filing records how well it was actually built.
- Private disputes — only complaints escalated to the authority appear here.
- What it will be worth — the record is the past; it does not price the future.
- Construction progress — RERA Assam does not publish quarterly progress reports. How far along it actually is cannot be read here.