Complete project overview

RERA Telangana · Registration filing
Units
1 units
Saleable area
112–182 sq mper unit, as filed
Floors
5
Land area
3,992 sq m
Built-up area
12,579 sq m

Timeline

RERA approvedNov 2022
Proposed completionNov 2028
TodayJul 2026
Construction progress

54% overall, as filed

Podiums0%
Flat fit-out0%
Stairs & lifts0%
External finishes30%
OC-readiness30%
Internal finishes80%
Excavation100%
Basement & plinth100%
Stilt floor100%
Superstructure100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.
02

Builder’s track record

RERA Telangana · Promoter registration

STAR INFRA DEVELOPERS

PartnershipPromoter type
Medchal-Malkajgiri, TelanganaBased in
1Projects
1City
2022–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RERA Telangana · Registration filing
Locality
Chowdariguda
Village
Korremula
Mandal
Ghatkesar
District
Medchal-Malkajgiri
Pincode
500088
North boundary
Land of Star Infra Developers
East boundary
30 feet wide Road
South boundary
Neighbours Land of Existing Layout
West boundary
Neighbours Land
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 3.6km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 3.2 km · Hyderabad-Janagam HighwayNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
Canal 617 mRiver 1.2 km · Musi RiverWater body 1.3 km
distances only — not a flood assessment
Government land classification

Land here includes House Sites (residential), plus Dry land, Wet Land double crop, Coconut Garden, Agricultural Land fit for H.S., Land abutting NH/SH/ZPP/MPP. The state classes land per survey— confirm your plot’s survey number is House Sites.

Telangana Registration & Stamps
Declared external development
Water supply100%
Sewerage (Chamber,…50%
Rainwater50%
Electricity50%
Roads0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Renewable energy0%
Fire safety0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
Price analysisno declared cost on this filing — one government benchmark below

This state’s RERA filing carries no declared build cost at all — nothing to turn into a per-unit or per-sq-ft figure here. The one real, government-sourced number below is the closest thing to a benchmark this record can offer.

Government guidance value
₹2,000/sq ydHouse Sites

₹2,392/sq m · effective Jan 2013

The state’s minimum value for this village’s land, set for stamp duty — a floor, not a market price. Source: Telangana Registration & Stamps.

04

Planning authority

RERA Telangana · Approved building plan

Hyderabad Metropolitan Development Authority (HMDA)

Urban Development Authority
Building Permit
Survey no. 793/A/1A and 793/A/1A/1
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

HMDA

Urban Development Authority · Hyderabad metropolitan periphery

Has approved 3,643 RERA projectsabout 1 in 3 in Telangana.

an apartments market72% apartments · 28% plotted layouts. Apartments like yours are this body's core business.

Builders
2,462
On record
3,98,695 flats · 1,96,015 plots
Reach
71 mandals
Since
2016

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.