01
Complete project overview
UP-RERA · Registration filing- Units
- 629 units
- Unit mix
- 484 × 4 BHK · 120 × 3 BHK · 25 × SHOP
- Carpet area
- 14–189 sq mper unit, as filed
- Floors
- 31
- Blocks
- 6
- Land area
- 32,292 sq m
Timeline
Proposed completionMar 2030
BuildingFloorTypeArea sq mCount
CommercialGFSHOP144
CommercialGFSHOP1518
CommercialGFSHOP151
CommercialGFSHOP151
CommercialGFSHOP151
Tower B214 BHK1894
Tower B224 BHK1894
Tower B234 BHK1894
Tower B244 BHK1894
Tower B254 BHK1894
Tower B264 BHK1894
Tower B274 BHK1894
Tower B284 BHK1894
Tower B294 BHK1894
Tower B2104 BHK1894
Tower B2114 BHK1894
Tower B2124 BHK1894
Tower B2134 BHK1894
Tower B2144 BHK1894
Tower B2154 BHK1894
Tower B2164 BHK1894
Tower B2174 BHK1894
Tower B2184 BHK1894
Tower B2194 BHK1894
Tower B2204 BHK1894
Tower B2214 BHK1894
Tower B2224 BHK1894
Tower B2234 BHK1894
Tower B2244 BHK1894
Tower B2254 BHK1894
Tower B2264 BHK1894
Tower B2274 BHK1894
Tower B2284 BHK1894
Tower B2294 BHK1894
Tower C114 BHK1504
Tower C124 BHK1504
Tower C134 BHK1504
Tower C144 BHK1504
Tower C154 BHK1504
Tower C164 BHK1504
Tower C174 BHK1504
Tower C184 BHK1504
Tower C194 BHK1504
Tower C1104 BHK1504
Tower C1114 BHK1504
Tower C1124 BHK1504
Tower C1134 BHK1504
Tower C1144 BHK1504
Tower C1154 BHK1504
Tower C1164 BHK1504
Tower C1174 BHK1504
Tower C1184 BHK1504
Tower C1194 BHK1504
Tower C1204 BHK1504
Tower C1214 BHK1504
Tower C1224 BHK1504
Tower C1234 BHK1504
Tower C1244 BHK1504
Tower C1254 BHK1504
Tower C1264 BHK1504
Tower C1274 BHK1504
Tower C1284 BHK1504
Tower C1294 BHK1504
Tower C1304 BHK1504
Tower C214 BHK1504
Tower C224 BHK1504
Tower C234 BHK1504
Tower C244 BHK1504
Tower C254 BHK1504
Tower C264 BHK1504
Tower C274 BHK1504
Tower C284 BHK1504
Tower C294 BHK1504
Tower C2104 BHK1504
Tower C2114 BHK1504
Tower C2124 BHK1504
Tower C2134 BHK1504
Tower C2144 BHK1504
Tower C2154 BHK1504
Tower C2164 BHK1504
Tower C2174 BHK1504
Tower C2184 BHK1504
Tower C2194 BHK1504
Tower C2204 BHK1504
Tower C2214 BHK1504
Tower C2224 BHK1504
Tower C2234 BHK1504
Tower C2244 BHK1504
Tower C2254 BHK1504
Tower C2264 BHK1504
Tower C2274 BHK1504
Tower C2284 BHK1504
Tower C2294 BHK1504
Tower C2304 BHK1504
Tower C2314 BHK1504
Tower C314 BHK1504
Tower C324 BHK1504
Tower C334 BHK1504
Tower C344 BHK1504
Tower C354 BHK1504
Tower C364 BHK1504
Tower C374 BHK1504
Tower C384 BHK1504
Tower C394 BHK1504
Tower C3104 BHK1504
Tower C3114 BHK1504
Tower C3124 BHK1504
Tower C3134 BHK1504
Tower C3144 BHK1504
Tower C3154 BHK1504
Tower C3164 BHK1504
Tower C3174 BHK1504
Tower C3184 BHK1504
Tower C3194 BHK1504
Tower C3204 BHK1504
Tower C3214 BHK1504
Tower C3224 BHK1504
Tower C3234 BHK1504
Tower C3244 BHK1504
Tower C3254 BHK1504
Tower C3264 BHK1504
Tower C3274 BHK1504
Tower C3284 BHK1504
Tower C3294 BHK1504
Tower C3304 BHK1504
Tower C3314 BHK1504
Tower D113 BHK1214
Tower D123 BHK1214
Tower D133 BHK1214
Tower D143 BHK1214
Tower D153 BHK1214
Tower D163 BHK1214
Tower D173 BHK1214
Tower D183 BHK1214
Tower D193 BHK1214
Tower D1103 BHK1214
Tower D1113 BHK1214
Tower D1123 BHK1214
Tower D1133 BHK1214
Tower D1143 BHK1214
Tower D1153 BHK1214
Tower D1163 BHK1214
Tower D1173 BHK1214
Tower D1183 BHK1214
Tower D1193 BHK1214
Tower D1203 BHK1214
Tower D1213 BHK1214
Tower D1223 BHK1214
Tower D1233 BHK1214
Tower D1243 BHK1214
Tower D1253 BHK1214
Tower D1263 BHK1214
Tower D1273 BHK1214
Tower D1283 BHK1214
Tower D1293 BHK1214
Tower D1303 BHK1214
Complete project overview — done
02
Builder’s track record
UP-RERA · Promoter registrationTHEMECOUNTY PRIVATE LIMITED
CompanyPromoter type
5Registered projects
2Projects
1City
2025–presentActive
Timelineevery project, start → promised completion
2025202620272028202920302031today
Builder DNAthe whole portfolio, summed
1,039 homeson the public record across 2 projects
51,561 sq mland declared
₹1733.08 Crdeclared build cost
Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
Builder's track record — done
03
Location & price analysis
UP-RERA · Registration filing- District
- Gautam Buddha Nagar
- Tehsil
- Dadri
What’s nearbySchoolsNo schools within 2km
HealthcareHospital 1.9km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting aroundExpressway 3.2 km · Grand Trunk RoadRailway line 4.3 kmNo metro or railway within 5kmLimited bus connectivity nearby
Water & environmentWater body 487 mCanal 3.3 km
distances only — not a flood assessment Price analysisdeclared build cost — not a sale price
₹1091.81 Cr declared to build 629 flats. What that works out to:
₹1.74 Crdeclared cost per flatall-in — land + construction
Location & price analysis — done
04
Planning authority
UP-RERA · Approved building planGhaziabad Development Authority
Development Authorityapproved 4 Apr 2025 · 1 yr ago
Building Permit no. GDA/BP/24-25/1602
The occupancy certificate — the proof that isn’t hereA sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.
Verify it yourself — look up plan GDA/BP/24-25/1602 on the approving authority’s portal to confirm the sanction.
Planning authority — done
Complaints registerNone on record with UP-RERA against this project.
Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.
What this record cannot tell you
- Build quality — no filing records how well it was actually built.
- Private disputes — only complaints escalated to the authority appear here.
- What it will be worth — the record is the past; it does not price the future.
- Construction progress — UP-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.