HORIZONMarkets
01

Complete project overview

UP-RERA · Registration filing
Units
128 units
Unit mix
120 × 3 BHK · 8 × 2 BHK
Carpet area
75–113 sq mper unit, as filed
Floors
15
Blocks
2
Land area
4,004 sq m

Timeline

RERA registeredJul 2025
Project startedOct 2025
Proposed completionNov 2031
TodayJul 2026

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

128 units across 72 batches
BuildingFloorTypeArea sq mCount
TOWER 8GF2 BHK751
TOWER 8GF2 BHK951
TOWER 8GF3 BHK1131
TOWER 8GF3 BHK941
TOWER 812 BHK751
TOWER 812 BHK951
TOWER 813 BHK1131
TOWER 813 BHK941
TOWER 823 BHK1132
TOWER 823 BHK942
TOWER 833 BHK1132
TOWER 833 BHK942
TOWER 843 BHK1132
TOWER 843 BHK942
TOWER 853 BHK1132
TOWER 853 BHK942
TOWER 863 BHK1132
TOWER 863 BHK942
TOWER 873 BHK1132
TOWER 873 BHK942
TOWER 883 BHK1132
TOWER 883 BHK942
TOWER 893 BHK1132
TOWER 893 BHK942
TOWER 8103 BHK1132
TOWER 8103 BHK942
TOWER 8113 BHK1132
TOWER 8113 BHK942
TOWER 8123 BHK1132
TOWER 8123 BHK942
TOWER 8133 BHK1132
TOWER 8133 BHK942
TOWER 8143 BHK1132
TOWER 8143 BHK942
TOWER 8153 BHK1132
TOWER 8153 BHK942
TOWER 9GF2 BHK751
TOWER 9GF2 BHK951
TOWER 9GF3 BHK1131
TOWER 9GF3 BHK941
TOWER 912 BHK751
TOWER 912 BHK951
TOWER 913 BHK1131
TOWER 913 BHK941
TOWER 923 BHK1132
TOWER 923 BHK942
TOWER 933 BHK1132
TOWER 933 BHK942
TOWER 943 BHK1132
TOWER 943 BHK942
TOWER 953 BHK1132
TOWER 953 BHK942
TOWER 963 BHK1132
TOWER 963 BHK942
TOWER 973 BHK1132
TOWER 973 BHK942
TOWER 983 BHK1132
TOWER 983 BHK942
TOWER 993 BHK1132
TOWER 993 BHK942
TOWER 9103 BHK1132
TOWER 9103 BHK942
TOWER 9113 BHK1132
TOWER 9113 BHK942
TOWER 9123 BHK1132
TOWER 9123 BHK942
TOWER 9133 BHK1132
TOWER 9133 BHK942
TOWER 9143 BHK1132
TOWER 9143 BHK942
TOWER 9153 BHK1132
TOWER 9153 BHK942

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

UP-RERA · Promoter registration

PRIVUE BUILDERS PRIVATE LIMITED; LONGTAIL CAPITAL LIMITED; P J METALS PRIVATE LIMITED

CompanyPromoter type
3Registered projects
3Projects
1City
2024–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
476 homeson the public record across 3 projects
18,516 sq mland declared
₹486.94 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

UP-RERA · Registration filing
District
Lucknow
Tehsil
Sarojini Nagar
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 2.5km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 1.2 km · Sultanpur RoadPrimary road 3.2 kmRailway line 798 m · Varanasi–Sultanpur–Lucknow lineRailway station 796m away (Bakkas)Limited bus connectivity nearby
Water & environment
Canal 570 mWater body 1.7 km
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹126.88 Cr declared to build 128 flats. What that works out to:

₹99.13 Lakhdeclared cost per flatall-in — land + construction

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

UP-RERA · Approved building plan

Lucknow Development Authority

Development Authority
approved 9 Jun 2025 · 1 yr ago
Building Permit no. Group Housing/15194/LDA/BP/24-25/3990/13022025
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan Group Housing/15194/LDA/BP/24-25/3990/13022025 on the approving authority’s portal to confirm the sanction.

Complaints register

None on record with UP-RERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — UP-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.