RERA Karnataka · Registration filing
Status
New Project Launch
Units
92 units
Unit mix
68 × 2 BHK · 20 × 3 BHK · 4 × 1 BHK
Towers
1
Floors
3
Land area
6,045 sq m
Built-up area
12,328 sq m
FAR sanctioned
1.495
Covered area
2,595 sq m
Open area
3,450 sq m
Land parcels
9 survey nos

Timeline

Project startedSep 2025
RERA registeredOct 2025
Proposed completionDec 2028
TodayJul 2026
Construction progress

46% overall, as filed

Finishing0%
Amenities0%
Common areas3%
External infra6%
Super-structure14%
Internal infra15%
Sub-structure100%
From the promoter's latest quarterly progress report filed with RERA Karnataka — % complete overall and by stage, as of that filing. A dated snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

92 units across 3 batches
TypeArea sq mCount
3 BHK9820
1 BHK374
2 BHK7068

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

RERA Karnataka · Promoter registration

JP Housing Corporation

Partnership FirmPromoter type
Bengaluru RuralBased in
5Projects
1City
2023–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
304 homeson the public record across 5 projects
42,300 sq mbuilt-up filed
19,247 sq mland declared
₹162.15 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Local Planning AuthorityTown & Country Planning (DTCP)3 of 5 projects
Hoskote Planning AuthorityTown & Country Planning (DTCP)this project2 of 5 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RERA Karnataka · Registration filing
Taluk
Hosakote
District
Bengaluru Rural
Pincode
562114
Address
KHATA No.15463/206/7, 206/8, 206/9, 206/10, 206/11, 206/26, 206/27, 206/31(206/7(OLD) & PID No.34-532-1078A , Sy Nos.206/7,206/8,206/9,206/10,206/11,206/26,206/27 & 206/31(206/7(OLD) OF HOSKOTE VILLAGE,KASABA HOBLI , Hosakote , Bengaluru Rural, Karnataka - 562114
North boundary
Road
East boundary
Road and Survey No.206/29,206/30,206/2,206/14
South boundary
Survey No.206/4
West boundary
NALA
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 1.3km away · Clinic within 2km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 373 m · Dabaspete - Hosur HighwayPrimary road 1.4 km · Old Dabaspete - Hosur HighwayNo metro or railway within 5kmBus stop within 1km
Water & environment
Water body 131 mRiver 983 m · Dakshina Pinakini
distances only — not a flood assessment
Land, title & encumbrance
LandJoint development (JDA) — built on the owner’s land by agreement
ConversionConverted to non-agricultural
LitigationDeclared free of litigation
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
Price analysisdeclared build cost — not a sale price

₹50.19 Cr declared to build 92 flats. What that works out to:

₹54.55 Lakhdeclared cost per flatall-in — land + construction
₹3,782/sq ftof built-up area₹40,708/sq m
24%of the cost is land₹1,858/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RERA Karnataka · Approved building plan

Hoskote Planning Authority

Town & Country Planning (DTCP)
approved 16 Apr 2025 · 1 yr ago
Building Permit no. HSK-LBPAS-10776/24-25/ALTSurvey no. 206/7 (206/1 old)
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan HSK-LBPAS-10776/24-25/ALT on the approving authority’s portal to confirm the sanction.

The approving body, at scale

Hoskote Planning Authority

Town & Country Planning

Has approved 38 RERA projects0.4% of Karnataka.

a mixed market61% apartments · 39% plotted layouts.

Builders
36
On record
3,524 flats · 1,940 plots
Reach
2 taluks
Since
2025

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Complaints register

None on record with RERA Karnataka against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.