HORIZONMarkets
01

Complete project overview

RAJ-RERA · Registration filing
Land area
15,200 sq m
Description
BLOCK NO 1,2,3 HAS BEEN COMPLETED AND POSSESSION HAS BEEN ALSO OFFERED IN THESE BLOCKS. ONLY WORK OF BLOCK NUMBER 4 IS UNDER PROCESS.

Timeline

Proposed completionApr 2017
RERA registeredNov 2017
TodayJul 2026
02

Builder’s track record

RAJ-RERA · Promoter registration

KALKA HOME DEVELOPERS PRIVATE LIMITED

OrganisationPromoter type
Alwar, RajasthanBased in
2Projects
1City
2017–2019Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
2 projectson the public record across 2 projects
39,288 sq mbuilt-up filed
27,783 sq mland declared
₹145.30 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
Khasra No- 231, Teh- Tijara, Distt- Alwar, Village-Thada, Teh- Tijara (Bhiwadi), Tijara, Alwar, 301019
Taluka
Tijara
District
Alwar
Pincode
301019
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 141m away · 1 clinic within 1km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 969 m · SohnaroadPrimary road 1.1 kmRailway line 4.4 km · Western Dedicated Freight CorridorNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
Water body 4.6 km
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹95.00 Cr declared. What that works out to:

5%of the cost is land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RAJ-RERA · Approved building plan
Building Permitapproved 6 Nov 2017 · 8 yrs ago

The promised possession date (10 Apr 2017) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.