HORIZONMarkets
01

Complete project overview

UP-RERA · Registration filing
Units
69 units
Unit mix
41 × 3 BHK · 28 × 2 BHK
Carpet area
62–88 sq mper unit, as filed
Floors
6
Land area
2,559 sq m

Timeline

Project startedApr 2015
RERA registeredAug 2017
Proposed completionDec 2018
TodayJul 2026

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

69 units across 28 batches
BuildingFloorTypeArea sq mCount
1GF2 BHK624
1GF3 BHK824
1GF3 BHK881
1GF3 BHK861
112 BHK624
113 BHK824
113 BHK881
113 BHK861
122 BHK624
123 BHK824
123 BHK881
123 BHK861
132 BHK624
133 BHK824
133 BHK881
133 BHK861
142 BHK624
143 BHK824
143 BHK881
143 BHK861
152 BHK624
153 BHK824
153 BHK881
153 BHK861
162 BHK624
163 BHK881
163 BHK861
163 BHK823

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

UP-RERA · Promoter registration

SPVP INFRA DEVELOPERS

Proprietorship FirmPromoter type
1Registered projects
1Projects
1City
2017–2018Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

UP-RERA · Registration filing
District
Bareilly
Tehsil
Bareilly
Site access
Located on 18m wide Alakhnath Road (Bareilly Qila Bye-pass Road)
What’s nearby
SchoolsNo schools within 2km · Library 2.0km away
HealthcareHospital 165m away · 1 clinic within 1km
LifestyleNo parks within 2km · Gym or sports centre 2.0km away
ShoppingNo supermarket within 2km · Bank 821m away
Getting around
Expressway 1.3 kmPrimary road 932 mRailway line 2.2 kmRailway station 2.6km away (Izatnagar Junction)Limited bus connectivity nearby
Water & environment
Water body 1.6 kmRiver 2.5 km
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹25.00 Cr declared to build 69 flats. What that works out to:

₹36.23 Lakhdeclared cost per flatall-in — land + construction

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

UP-RERA · Approved building plan
approved 10 Jun 2014 · 12 yrs ago
Building Permit no. 127/2/GH/13

The promised possession date (31 Dec 2018) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan 127/2/GH/13 on the approving authority’s portal to confirm the sanction.

Complaints register

None on record with UP-RERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — UP-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.