HORIZON
Share

Kiara

RAJ/P/2020/1285 · RAJ-RERA · https://gethorizon.in/projects/kiara-sanganer-jaipur-2tz1424d

01

Complete project overview

RAJ-RERA · Registration filing
Project name
Kiara
Land area
2,231 sq m

Timeline

Construction startApr 2020
RERA registeredJul 2020
Proposed completionDec 2024
TodaySep 2026
02

Builder’s track record

RAJ-RERA · Builder registration

Lalit Menghnani

IndividualPromoter type
Jaipur, RajasthanBased in
1Projects
1City
2020–2024Active
Timelineevery project, start → promised completion

The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
625/2, 626/1, Village Tilawala, Sanganer, Jaipur, 302033
Taluka
Sanganer
District
Jaipur
Pincode
302033
What’s nearby
SchoolsNearest school 1.4km away · Library 1.8km away
HealthcareHospital 542m away · 2 clinics within 1km
LifestylePark 1.2km away
ShoppingNo supermarket within 2km · Bank 697m away
Getting around
Expressway 4.0 kmPrimary road 4.7 km · Calgiri RoadRailway line 2.1 kmRailway station 2.6km away (Getor Jagatpura)Bus stop within 500m
Price analysisdeclared build cost — not a sale price

₹16.19 Cr declared. What that works out to:

18%of the cost is land

This is what the builder filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Government Guidance Rate

Rajasthan registration department

In Rajasthan it’s called the DLC rate.

No government guidance rate is shown for this project.

Rajasthan's schedule is in Horizon's record, but this project's filed location couldn't be matched to one place with certainty — so no figure is shown rather than a guess.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

RAJ-RERA · Approved building plan
Building Permitapproved 30 Jul 2020 · 6 yrs ago

The promised possession date (31 Dec 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

07

Other projects nearby

The register · within 25 km

414 residential projects still under way within 25 km. Step out ring by ring:

4 projects within 1 km — showing the nearest 4.

SanganerGroup Housing

MAHI APARTMENT

RAJASTHAN HOUSING BOARD

Feb 2023registered
Dec 2028target completion
Declared cost₹109.49 CrScale325 flatsAuthorityRAJ-RERA
JaipurGroup Housing

Parth Elegance

Parth Sarthi Industries

Jan 2024registered
Dec 2026target completion
Declared cost₹13.02 CrScale42 flatsAuthorityRAJ-RERA
JaipurMixed (Residential And Commercial)

THE INDEX

SANKALP INFRAHEIGHTS PRIVATE LIMITED

Sep 2021registered
Aug 2026target completion
Declared cost₹101.26 CrScale358 flatsAuthorityRAJ-RERA
SanganerGroup Housing

Sankalp Alexa Homes

sankalp builders

Apr 2021registered
Apr 2026target completion
Declared cost₹28.37 CrScale183 flatsAuthorityRAJ-RERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. This project’s coordinate is approximate, so distances are rough.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.