HORIZONMarkets
01

Complete project overview

RAJ-RERA · Registration filing
Plots
63 plots
Land area
14,032 sq m
Description
In the project total area is 14032 sq.m out of which open area is 4843 sq.m. Out of total area 14032 sq.m 12.50% has been mortgaged by UIT that means 7 plots has been mortgaged (plot no. A-33,34,35,36,37,38 and 39) out of 63 plots.

Timeline

Construction startMar 2023
RERA registeredMar 2023
Proposed completionMar 2025
TodayJul 2026

Find your plot

Filed by type and size, in the batches the promoter registered — not a per-plot listing. Look yours up.

63 plots across 36 batches
TypeArea sq mCount
Plot1271
Plot2,60617
Plot2411
Plot2131
Plot5954
Plot1321
Plot2901
Plot1281
Plot1846
Plot1541
Plot6134
Plot1591
Plot1531
Plot1271
Plot1601
Plot1551
Plot1861
Plot1271
Plot1751
Plot1601
Plot1471
Plot1281
Plot2001
Plot1641
Plot1561
Plot1561
Plot1041
Plot1481
Plot2101
Plot1551
Plot1591
Plot1791
Plot1291
Plot1531
Plot1441
Plot1721

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each size exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

RAJ-RERA · Promoter registration

ABDUL GAFAR

IndividualPromoter type
Sikar, RajasthanBased in
1Projects
1City
2023–2025Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
836/830, SHIVSINGHPURA, SHIVSINGHPURA, Sikar, Sikar, 332001
Village
SHIVSINGHPURA
Taluka
Sikar
District
Sikar
Pincode
332001
What’s nearby
SchoolsNo schools within 2km · Library 2.0km away
HealthcareNearest hospital 2.4km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Primary road 166 mRailway line 2.4 kmRailway station 4.1km away (Sikar Railway Station)Limited bus connectivity nearby
Price analysisdeclared build cost — not a sale price

₹1.09 Cr declared to build 63 plots. What that works out to:

₹1.73 Lakhdeclared cost per plotall-in — land + construction
₹72/sq ftof plotted area₹777/sq m
53%of the cost is land₹38/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RAJ-RERA · Approved building plan

Urban Improvement Trust

Urban Improvement Trust
Layout Permitapproved 29 Mar 2023 · 3 yrs ago

The promised possession date (31 Mar 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Urban Improvement Trust

A city-level Urban Improvement Trust — Rajasthan's town-development body in cities without a development authority. It has approved 612 RERA projects across 20 districts about 1 in 4 in Rajasthan.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.