Complete project overview

RERA Telangana · Registration filing
Units
1 units
Saleable area
175 sq mper unit, as filed
Floors
5
Land area
585 sq m
Built-up area
1,484 sq m

Timeline

RERA approvedDec 2021
Proposed completionDec 2024
TodayJul 2026
Construction progress

39% overall, as filed

Podiums0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Superstructure90%
Excavation100%
Basement & plinth100%
Stilt floor100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.
02

Builder’s track record

RERA Telangana · Promoter registration

KRANTI INFRA

PartnershipPromoter type
Medchal-Malkajgiri, TelanganaBased in
3Projects
1City
2021–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
324 homeson the public record across 3 projects
54,621 sq mbuilt-up filed
20,706 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
KAPRA
Mandal
Kapra
District
Medchal-Malkajgiri
Pincode
500094
North boundary
PLOT 87 B 87 C
East boundary
PLOT NO 89 A
South boundary
30 FEET WIDE ROAD
West boundary
PLOT NO 86 A
What’s nearby
Schools1 school within 1km
HealthcareHospital 916m away · Clinic within 2km
LifestyleNo parks within 2km · Gym or sports centre 982m away · 3 restaurants and cafes within 1km
ShoppingSupermarket 1.2km away · Mall 1.4km away · Convenience store within 1km
Getting around
Primary road 3.1 km · Kushaiguda RoadRailway line 2.2 kmRailway station 2.2km away (Neredmet)Limited bus connectivity nearby
Water & environment
Water body 500 m · Kapra lake
distances only — not a flood assessment
Declared external development
Water supply100%
Roads0%
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Greater Hyderabad Municipal Corporation (GHMC)

Municipal / Corporation
Building Permit
Survey no. 591,595,596

The promised possession date (13 Dec 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

GHMC

Municipal Corporation · Hyderabad city core

Has approved 3,102 RERA projectsabout 1 in 4 in Telangana.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,994
On record
2,20,211 flats · 3,387 plots
Reach
65 mandals
Since
2016

More apartment-heavy than Telangana overall — 99% apartments here vs 66% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.