HORIZONMarkets
01

Complete project overview

RERA Telangana · Registration filing
Units
25 units
Unit mix
25 × 2BHK
Saleable area
129–132 sq mper unit, as filed
Floors
5
Land area
1,208 sq m
Built-up area
2,685 sq m

Timeline

RERA approvedMay 2022
Proposed completionMay 2025
TodayJul 2026
Construction progress

0% overall, as filed

Excavation0%
Basement & plinth0%
Podiums0%
Stilt floor0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

25 of 25 available
BuildingFloorTypeArea sq mAvailable
LAKE BREEZE SESHADRI12BHK1323 of 3
LAKE BREEZE SESHADRI12BHK1292 of 2
LAKE BREEZE SESHADRI22BHKmortgaged1322 of 2
LAKE BREEZE SESHADRI22BHK1321 of 1
LAKE BREEZE SESHADRI22BHK1291 of 1
LAKE BREEZE SESHADRI22BHKmortgaged1291 of 1
LAKE BREEZE SESHADRI32BHK1323 of 3
LAKE BREEZE SESHADRI32BHK1292 of 2
LAKE BREEZE SESHADRI42BHK1323 of 3
LAKE BREEZE SESHADRI42BHK1292 of 2
LAKE BREEZE SESHADRI52BHK1323 of 3
LAKE BREEZE SESHADRI52BHK1292 of 2

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

RUDRAKSH MEGACORP PRIVATE LIMITED

CompanyPromoter type
Hyderabad, TelanganaBased in
3Projects
1City
2018–2025Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
50 homes · 231 plotson the public record across 3 projects
5,403 sq mbuilt-up filed
77,958 sq mplotted area
80,438 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
Shamirpet
Mandal
Shamirpet
District
Medchal-Malkajgiri
Pincode
500078
North boundary
Road Width - 18
East boundary
Road Width 10-06
South boundary
Plot No 79 and 86
West boundary
Road Width 10-06
What’s nearby
SchoolsNo schools within 2km
HealthcareNo hospital within 5km · 1 clinic within 1km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Primary road 157 mNo metro or railway within 5km2 bus stops within 500m
Water & environment
Water body 585 mRiver 1.4 km
distances only — not a flood assessment
Declared external development
Roads0%
Water supply0%
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Hyderabad Metropolitan Development Authority (HMDA)

Urban Development Authority
Building Permit
Survey no. 1247(P) and 1249

The promised possession date (9 May 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

HMDA

Urban Development Authority · Hyderabad metropolitan periphery

Has approved 3,643 RERA projectsabout 1 in 3 in Telangana.

an apartments market72% apartments · 28% plotted layouts. Apartments like yours are this body's core business.

Builders
2,462
On record
3,98,695 flats · 1,96,015 plots
Reach
71 mandals
Since
2016

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.