Complete project overview

RERA Telangana · Registration filing
Units
14 units
Unit mix
8 × 2 Bedroom, 5 × 3 Bedroom, 1 × 4 Bedroom
Saleable area
100–200 sq mper unit, as filed
Floors
5
Land area
650 sq m
Built-up area
553 sq m
Road widening
97 sq mland set aside for road widening

Timeline

RERA approvedJun 2021
Proposed completionJun 2024
TodayJul 2026
Construction progress

100% overall, as filed

Excavation100%
Basement & plinth100%
Podiums100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

14 of 14 available
BuildingFloorTypeArea sq mAvailable
LAXMAREDDY RESIDENCY13 Bedroom1251 of 1
LAXMAREDDY RESIDENCY14 Bedroom2001 of 1
LAXMAREDDY RESIDENCY23 Bedroommortgaged1251 of 1
LAXMAREDDY RESIDENCY22 Bedroommortgaged1002 of 2
LAXMAREDDY RESIDENCY33 Bedroom1251 of 1
LAXMAREDDY RESIDENCY32 Bedroom1002 of 2
LAXMAREDDY RESIDENCY43 Bedroom1251 of 1
LAXMAREDDY RESIDENCY42 Bedroom1002 of 2
LAXMAREDDY RESIDENCY53 Bedroom1251 of 1
LAXMAREDDY RESIDENCY52 Bedroom1002 of 2

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

SWATHI CONSTRUCTIONS

CompanyPromoter type
Medchal-Malkajgiri, TelanganaBased in
4Projects
3Cities
2021–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
129 homes · 42 plotson the public record across 4 projects
14,695 sq mbuilt-up filed
12,209 sq mplotted area
18,740 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Hyderabad Metropolitan Development Authority (HMDA)Urban Development Authority2 of 4 projects
Directorate of Town & Country Planning (DTCP)Town & Country Planning (DTCP)1 of 4 projects
Greater Hyderabad Municipal Corporation (GHMC)Municipal / Corporationthis project1 of 4 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
POCHARAM
Mandal
Malkajgiri
District
Medchal-Malkajgiri
Pincode
500098
North boundary
15 FT WIDE ROAD
East boundary
30 FT WIDE ROAD
South boundary
25 FT WIDE ROAD
West boundary
NEIGHBOURS LAND
What’s nearby
SchoolsNearest school 1.1km away · College or university 1.7km away
HealthcareHospital 1.7km away · Clinic within 2km · Pharmacy within 1km
LifestyleNo parks within 2km
ShoppingSupermarket 1.3km away · Mall 1.9km away · Bank 342m away
Getting around
Expressway 1.7 km · Hyderabad-Janagam HighwayMetro station 4.9km away (Uppal)Limited bus connectivity nearby
Water & environment
Water body 239 mCanal 636 m
distances only — not a flood assessment
Declared external development
Water supply100%
Sewerage (Chamber,…100%
Rainwater100%
Rainwater100%
Roads0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Greater Hyderabad Municipal Corporation (GHMC)

Municipal / Corporation
Building Permit
Survey no. 1/C/2

The promised possession date (11 Jun 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

GHMC

Municipal Corporation · Hyderabad city core

Has approved 3,102 RERA projectsabout 1 in 4 in Telangana.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,994
On record
2,20,211 flats · 3,387 plots
Reach
65 mandals
Since
2016

More apartment-heavy than Telangana overall — 99% apartments here vs 66% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.