Complete project overview

RERA Telangana · Registration filing
Units
50 units
Unit mix
50 × 3BHK
Saleable area
163 sq mper unit, as filed
Floors
5
Land area
3,025 sq m
Built-up area
7,494 sq m
Road widening
4 sq mland set aside for road widening

Timeline

RERA approvedJun 2023
Proposed completionJun 2026
TodayJul 2026
Construction progress

51.5% overall, as filed

Podiums0%
Flat fit-out10%
Stairs & lifts10%
External finishes10%
OC-readiness10%
Internal finishes75%
Excavation100%
Basement & plinth100%
Stilt floor100%
Superstructure100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

27 of 50 available
BuildingFloorTypeArea sq mAvailable
LEGALAs DOYEN ASCENT - EAGLE BLOCK13BHK16310 of 10
LEGALAs DOYEN ASCENT - EAGLE BLOCK23BHK1630 of 10
LEGALAs DOYEN ASCENT - EAGLE BLOCK33BHK16310 of 10
LEGALAs DOYEN ASCENT - EAGLE BLOCK43BHK1630 of 10
LEGALAs DOYEN ASCENT - EAGLE BLOCK53BHKmortgaged1636 of 6
LEGALAs DOYEN ASCENT - EAGLE BLOCK53BHK1631 of 4

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

DOYEN CONSTRUCTIONS PRIVATE LIMITED

CompanyPromoter type
Hyderabad, TelanganaBased in
14Projects
1City
2019–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
320 homes · 94 plotson the public record across 14 projects
50,418 sq mbuilt-up filed
27,934 sq mplotted area
49,425 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
Doyen's Colony
Village
Serilingampally
Mandal
Serilingampally
District
Ranga Reddy
Pincode
500019
North boundary
30 Feet Road
East boundary
40 Feet Road
South boundary
Amenities Block
West boundary
40 Feet Road
What’s nearby
SchoolsNearest school 1.2km away · College or university 555m away · Library 1.4km away
HealthcareHospital 909m away · 2 clinics within 1km · Pharmacy within 1km
LifestylePark 1.0km away · Gym or sports centre 1.9km away
ShoppingSupermarket 1.3km away · Mall 1.9km away · Convenience store within 1km
Getting around
Expressway 1.8 km · Gangaram - Chandanagar Road - Mumbai highwayPrimary road 472 m · Old Bombay RoadRailway line 966 mRailway station 1.1km away (Chandanagar)2 bus stops within 500m
Water & environment
Water body 153 m · Gopi Cheruvu
distances only — not a flood assessment
Government land classification

No residential (House Sites) class on record. The state classes this village’s land as Dry land. If it’s sold as residential plots, verify the layout’s conversion / approval.

Telangana Registration & Stamps
Declared external development
Sewerage (Chamber,…100%
Sewage100%
Water supply60%
Rainwater40%
Green Strip/TOT LO…10%
Roads0%
Street lighting0%
Community Building…0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Greater Hyderabad Municipal Corporation (GHMC)

Municipal / Corporation
Building Permit
Survey no. 79, 80, 81 AND 82 PART

The promised possession date (13 Jun 2026) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

GHMC

Municipal Corporation · Hyderabad city core

Has approved 3,102 RERA projectsabout 1 in 4 in Telangana.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,994
On record
2,20,211 flats · 3,387 plots
Reach
65 mandals
Since
2016

More apartment-heavy than Telangana overall — 99% apartments here vs 66% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.