RAJ-RERA · Registration filing
Units
83 units
Mix
7 × A-101, A-201, A-301, A-401, A-501, A-601, A-701 · 7 × A-102, A-202, A-302, A-402, A-502, A-602, A-702 · 7 × A-103, A-203, A-303, A-403, A-503, A-603, A-703 · 7 × A-104, A-204, A-304, A-404, A-504, A-604, A-704 · 7 × B-101, B-201, B-301, B-401, B-501, B-601, B-701 · 7 × B-103, B-203, B-303, B-403, B-503, B-603, B-703
Carpet area
127–509 sq mper-type range, as filed
Land area
13,481 sq m
Completion deadline extended
2 extensions on record — latest to 31 Mar 2027declared reason: other than force majeure
Description
1. In this project, there are total 4 Blocks A,B,C,D consist of total 2 Basements + G + 7 Floors. Initially, at the time of registration, the JDA had granted construction permission for only up to the 6th floor in Blocks A, B, C and D. Now the maps have been revised and the JDA has now granted the construction permission till 7th floor in Blocks A, B, C and D. 2. With the permission of RERA, project name has been changed from "LEHARIYA CRAFTED FOR BUSINESS" to "LEHARIYA"; and all declarations, undertakings, agreements, and other documents executed by the promoter with "LEHARIYA" as the name of this project will continue to hold good for this project now named as "LEHARIYA".

Timeline

Construction startOct 2023
RERA registeredOct 2023
Proposed completionMar 2025
TodayJul 2026

Find your unit

Filed by type and size, in the batches the promoter registered — not a per-unit listing. Look yours up.

83 units across 24 batches
BuildingTypeArea sq mCount
LEHARIYAA-B014061
LEHARIYAA-0013371
LEHARIYAA-0023081
LEHARIYAA-0032241
LEHARIYAA-0042901
LEHARIYAA-101, A-201, A-301, A-401, A-501, A-601, A-7013567
LEHARIYAA-102, A-202, A-302, A-402, A-502, A-602, A-7024507
LEHARIYAA-103, A-203, A-303, A-403, A-503, A-603, A-7032687
LEHARIYAA-104, A-204, A-304, A-404, A-504, A-604, A-7044147
LEHARIYAB-0012731
LEHARIYAB-0022781
LEHARIYAB-0031971
LEHARIYAB-101, B-201, B-301, B-401, B-501, B-601, B-7012857
LEHARIYAB-102, B-202, B-302, B-402, B-502, B-6023526
LEHARIYAB-103, B-203, B-303, B-403, B-503, B-603, B-7033037
LEHARIYAB-7022951
LEHARIYAC-0011881
LEHARIYAC-0022301
LEHARIYAC-101, C-201, C-301, C-401, C-501, C-601, C-7012437
LEHARIYAC-102, C-202, C-302, C-402, C-502, C-602, C-7023357
LEHARIYAD-0011991
LEHARIYAD-101, D-201, D-301, D-401, D-501, D-601, D-7013147
LEHARIYAFnB-0015091
LEHARIYAFnB-0021271

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

RAJ-RERA · Promoter registration

Shri Kalyan Buildmart Private Limited

OrganisationPromoter type
Jaipur, RajasthanBased in
1Projects
1City
2023–2025Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
Khasra No. 141/1, 142, 406/148, 403/148, 404/148, Chainpura, Sanganer, Jaipur, 302017
Village
Chainpura
Taluka
Sanganer
District
Jaipur
Pincode
302017
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 352m away · Clinic within 2km
LifestyleNo parks within 2km
ShoppingSupermarket 976m away · Mall 708m away
Getting around
Expressway 2.2 kmPrimary road 387 m · Jawahar CircleRailway line 1.3 kmRailway station 2.6km away (Getor Jagatpura)Bus stop within 500m
Price analysisdeclared build cost — not a sale price

₹196.68 Cr declared to build 83 flats. What that works out to:

₹2.37 Crdeclared cost per flatall-in — land + construction
₹3,499/sq ftof built-up area₹37,667/sq m
2%of the cost is land₹252/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RAJ-RERA · Approved building plan
Building Permitapproved 26 Oct 2023 · 2 yrs ago

The promised possession date (31 Mar 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.