Complete project overview

UP-RERA · Registration filing
Units
193 units
Unit mix
182 × 3 BHK · 11 × 2 BHK
Carpet area
63–80 sq mper unit, as filed
Floors
14
Blocks
4
Land area
6,461 sq m

Timeline

Project startedApr 2022
RERA registeredJul 2022
Proposed completionMar 2028
TodayJul 2026

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

193 units across 67 batches
BuildingFloorTypeArea sq mCount
Tower - A13 BHK804
Tower - A23 BHK804
Tower - A33 BHK804
Tower - A43 BHK804
Tower - A53 BHK804
Tower - A63 BHK804
Tower - A73 BHK804
Tower - A83 BHK804
Tower - A93 BHK804
Tower - A103 BHK804
Tower - A113 BHK804
Tower - A123 BHK804
Tower - A133 BHK804
Tower - A143 BHK804
Tower - B13 BHK784
Tower - B23 BHK784
Tower - B33 BHK784
Tower - B43 BHK784
Tower - B53 BHK784
Tower - B63 BHK784
Tower - B73 BHK784
Tower - B83 BHK784
Tower - B93 BHK784
Tower - B103 BHK784
Tower - B113 BHK784
Tower - B123 BHK784
Tower - B133 BHK784
Tower - B143 BHK784
Tower - C13 BHK783
Tower - C12 BHK631
Tower - C23 BHK783
Tower - C22 BHK631
Tower - C33 BHK783
Tower - C32 BHK631
Tower - C43 BHK783
Tower - C42 BHK631
Tower - C53 BHK783
Tower - C52 BHK631
Tower - C63 BHK783
Tower - C62 BHK631
Tower - C73 BHK783
Tower - C72 BHK631
Tower - C83 BHK783
Tower - C82 BHK631
Tower - C93 BHK783
Tower - C92 BHK631
Tower - C103 BHK783
Tower - C102 BHK631
Tower - C113 BHK783
Tower - C112 BHK631
Tower - C123 BHK783
Tower - C133 BHK783
Tower - C143 BHK783
Tower - D13 BHK772
Tower - D23 BHK772
Tower - D33 BHK772
Tower - D43 BHK772
Tower - D53 BHK772
Tower - D63 BHK772
Tower - D73 BHK772
Tower - D83 BHK772
Tower - D93 BHK772
Tower - D103 BHK772
Tower - D113 BHK772
Tower - D123 BHK772
Tower - D133 BHK772
Tower - D143 BHK772

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

UP-RERA · Promoter registration

AAKANSHA INFRATECH

Partnership FirmPromoter type
2Registered projects
2Projects
1City
2022–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
445 homeson the public record across 2 projects
12,461 sq mland declared
₹186.34 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

UP-RERA · Registration filing
District
Lucknow
Tehsil
Mohanlalganj
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 2.4km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 494 m · Sultanpur RoadPrimary road 3.2 km · Sultanpur RoadRailway line 1.8 km · Varanasi–Sultanpur–Lucknow lineRailway station 2.3km away (Bakkas)Limited bus connectivity nearby
Water & environment
Water body 1.2 kmCanal 1.5 km
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹52.20 Cr declared to build 193 flats. What that works out to:

₹27.05 Lakhdeclared cost per flatall-in — land + construction

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

UP-RERA · Approved building plan

Lucknow Development Authority

Development Authority
approved 18 Feb 2022 · 4 yrs ago
Building Permit no. Group Housing/03808/LDA/BP/21-22/0176/17122021
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan Group Housing/03808/LDA/BP/21-22/0176/17122021 on the approving authority’s portal to confirm the sanction.

Complaints register

1 complaint on UP-RERA’s register for this project.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — UP-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.