HORIZONMarkets
01

Complete project overview

RERA Assam · Registration filing
Registration category
NEWnew vs ongoing at registration
Land area
1,472 sq m
Local land measure
1BIGHA 0KATHA 10LECHA
RERA validity
31 Dec 2032

Timeline

RERA registeredNov 2025
Proposed completionDec 2032
TodayJul 2026
02

Builder’s track record

RERA Assam · Promoter registration

CHARTER RENOCON ASSOCIATES

Firm/ Proprietorship FirmPromoter type
1Projects
1City
2025–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RERA Assam · Registration filing
District
KAMRUP METRO
Mouza / circle
GUWAHATI
Town / village
GUWAHATI
Site address
JYOTIPATH, DHIRENPARA
Pincode
781009
What’s nearby
SchoolsNearest school 1.7km away
HealthcareHospital 92m away · Clinic within 2km · Pharmacy within 1km
LifestyleNo parks within 2km · 5 restaurants and cafes within 1km
ShoppingSupermarket 372m away · Convenience store within 1km · Bank 437m away
Getting around
Expressway 3.4 kmPrimary road 2.3 km · Maligaon FlyoverRailway line 2.2 kmRailway station 3.7km away (Kamakhya Junction)Limited bus connectivity nearby
Water & environment
Water body 798 mRiver 2.4 km
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹4.00 Cr declared. What that works out to:

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RERA Assam · Approved building plan

Guwahati Municipal Corporation

Municipal Corporation
Building Permitapproved 27 Aug 2024 · 1 yr ago
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Guwahati Municipal Corporation

Municipal corporation / board

Has approved 604 RERA projectsabout 1 in 1 in Assam, more than any other body in the state.

an apartments market98% apartments · 2% plotted layouts. Apartments like yours are this body's core business.

Builders
488
On record
45,695 flats · 10,758 plots
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Assam does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Assam does not publish a complaints register. This read cannot speak to them either way.