Complete project overview

RAJ-RERA · Registration filing
Land area
41,617 sq m
Description
1. This project plotted development project. Therefore there is no provision for parking in this project. 2. The conversion letter uploaded online is to be considered as approval letter. No separate approval letter is provided. 3. No plots are liable to be mortgage in this project to any government authority. 4. Sanctioned layout plan numbering is not correct, last number mentioned in layout plan is 160. however by individual counting of plots it comes to 128 plots, 16 shops and 1 institutional plot. Total inventory comes to 145. 5. Letter no. 1800/27/2016/351 and 1800/27/2016/450 as mentioned on copy of sanctioned layout were not issued to us. They are for internal use of Collector only.

Timeline

Construction startSep 2020
RERA registeredOct 2020
Proposed completionDec 2023
TodayJul 2026
02

Builder’s track record

RAJ-RERA · Promoter registration

Mangal Ram Meena

IndividualPromoter type
Jaipur, RajasthanBased in
1Projects
1City
2020–2023Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
408,409,410,414,416,419,421, VILLAGE RAITHAL, TEHSIL- PHAGI, RAITHAL, Phagi, Jaipur, 303904
Village
RAITHAL
Taluka
Phagi
District
Jaipur
Pincode
303904
What’s nearby
SchoolsNo schools within 2km
HealthcareNo hospital within 5km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Primary road 2.5 kmNo metro or railway within 5kmLimited bus connectivity nearby
Price analysisdeclared build cost — not a sale price

₹2.84 Cr declared. What that works out to:

₹63/sq ftof plotted area₹682/sq m
44%of the cost is land₹28/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RAJ-RERA · Approved building plan

Gram Panchayat

Gram Panchayat
Layout Permitapproved 20 Oct 2020 · 5 yrs ago

The promised possession date (31 Dec 2023) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Gram Panchayat

A village-level local body. It has approved 34 RERA projects across 5 districts 1.5% of Rajasthan.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.