HORIZONMarkets
01

Complete project overview

RERA Telangana · Registration filing
Units
93 units
Unit mix
64 × 2BHK, 29 × 3BHK
Saleable area
55–125 sq mper unit, as filed
Floors
5
Land area
4,166 sq m
Built-up area
10,492 sq m

Timeline

RERA approvedMay 2021
Proposed completionMay 2027
TodayJul 2026
Construction progress

37% overall, as filed

Podiums0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Superstructure70%
Excavation100%
Basement & plinth100%
Stilt floor100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

93 of 93 available
BuildingFloorTypeArea sq mAvailable
LOTUS RESIDENCY12BHK811 of 1
LOTUS RESIDENCY12BHK802 of 2
LOTUS RESIDENCY12BHK771 of 1
LOTUS RESIDENCY12BHK831 of 1
LOTUS RESIDENCY12BHK845 of 5
LOTUS RESIDENCY13BHK1251 of 1
LOTUS RESIDENCY12BHK561 of 1
LOTUS RESIDENCY12BHK551 of 1
LOTUS RESIDENCY12BHK761 of 1
LOTUS RESIDENCY13BHK961 of 1
LOTUS RESIDENCY13BHK1061 of 1
LOTUS RESIDENCY13BHK1061 of 1
LOTUS RESIDENCY13BHK1191 of 1
LOTUS RESIDENCY13BHK1071 of 1
LOTUS RESIDENCY22BHK811 of 1
LOTUS RESIDENCY22BHK802 of 2
LOTUS RESIDENCY22BHK771 of 1
LOTUS RESIDENCY22BHK831 of 1
LOTUS RESIDENCY22BHKmortgaged843 of 3
LOTUS RESIDENCY22BHK842 of 2
LOTUS RESIDENCY23BHK1251 of 1
LOTUS RESIDENCY22BHKmortgaged561 of 1
LOTUS RESIDENCY22BHKmortgaged551 of 1
LOTUS RESIDENCY22BHKmortgaged761 of 1
LOTUS RESIDENCY23BHKmortgaged961 of 1
LOTUS RESIDENCY23BHKmortgaged1061 of 1
LOTUS RESIDENCY23BHKmortgaged1061 of 1
LOTUS RESIDENCY23BHKmortgaged1191 of 1
LOTUS RESIDENCY23BHKmortgaged1071 of 1
LOTUS RESIDENCY32BHK811 of 1
LOTUS RESIDENCY32BHK802 of 2
LOTUS RESIDENCY32BHK771 of 1
LOTUS RESIDENCY32BHK831 of 1
LOTUS RESIDENCY32BHK865 of 5
LOTUS RESIDENCY33BHK1251 of 1
LOTUS RESIDENCY32BHK561 of 1
LOTUS RESIDENCY32BHK551 of 1
LOTUS RESIDENCY32BHK761 of 1
LOTUS RESIDENCY33BHK961 of 1
LOTUS RESIDENCY33BHK1061 of 1
LOTUS RESIDENCY33BHK1061 of 1
LOTUS RESIDENCY33BHK1191 of 1
LOTUS RESIDENCY33BHK1071 of 1
LOTUS RESIDENCY42BHK811 of 1
LOTUS RESIDENCY42BHK802 of 2
LOTUS RESIDENCY42BHK771 of 1
LOTUS RESIDENCY42BHK831 of 1
LOTUS RESIDENCY42BHK845 of 5
LOTUS RESIDENCY43BHK1251 of 1
LOTUS RESIDENCY42BHK561 of 1
LOTUS RESIDENCY42BHK551 of 1
LOTUS RESIDENCY42BHK761 of 1
LOTUS RESIDENCY43BHK961 of 1
LOTUS RESIDENCY43BHK1061 of 1
LOTUS RESIDENCY43BHK1191 of 1
LOTUS RESIDENCY43BHK1071 of 1
LOTUS RESIDENCY52BHK811 of 1
LOTUS RESIDENCY52BHK802 of 2
LOTUS RESIDENCY52BHK771 of 1
LOTUS RESIDENCY52BHK835 of 5
LOTUS RESIDENCY53BHK1251 of 1
LOTUS RESIDENCY52BHK561 of 1
LOTUS RESIDENCY52BHK551 of 1
LOTUS RESIDENCY52BHK761 of 1
LOTUS RESIDENCY53BHK961 of 1
LOTUS RESIDENCY53BHK1061 of 1
LOTUS RESIDENCY53BHK1061 of 1
LOTUS RESIDENCY53BHK1191 of 1
LOTUS RESIDENCY53BHK1071 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

PRESTIGE INFRA

PartnershipPromoter type
Hyderabad, TelanganaBased in
4Projects
2Cities
2020–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
93 homeson the public record across 4 projects
25,865 sq mbuilt-up filed
11,816 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Chiplun Municipal CouncilMunicipal Council1 of 2 projects
Hyderabad Metropolitan Development Authority (HMDA)Urban Development Authoritythis project1 of 2 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
KOMPALLY
District
Medchal-Malkajgiri
Pincode
500014
North boundary
CTS NO -
East boundary
CTS NO -
South boundary
ROAD WIDTH - 12
West boundary
CTS NO -
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 3.3km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 2.2 km · Nizamabad RoadPrimary road 1.8 km · Hyderabad - Karimnagar HighwayRailway line 970 mRailway station 2.1km away (Bolarum)Limited bus connectivity nearby
Water & environment
Water body 1.1 km
distances only — not a flood assessment
Declared external development
Roads0%
Water supply0%
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Hyderabad Metropolitan Development Authority (HMDA)

Urban Development Authority
Building Permit no. 040882/MED/R1/U6/HMDA/30112020Survey no. 119/PART
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan 040882/MED/R1/U6/HMDA/30112020 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

HMDA

Urban Development Authority · Hyderabad metropolitan periphery

Has approved 3,643 RERA projectsabout 1 in 3 in Telangana.

an apartments market72% apartments · 28% plotted layouts. Apartments like yours are this body's core business.

Builders
2,462
On record
3,98,695 flats · 1,96,015 plots
Reach
71 mandals
Since
2016

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.