HORIZONMarkets
01

Complete project overview

UP-RERA · Registration filing
Units
63 units
Unit mix
51 × 3 BHK · 12 × 2 BHK
Carpet area
65–97 sq mper unit, as filed
Floors
7
Blocks
2
Land area
4,800 sq m

Timeline

Project startedJul 2017
RERA registeredJul 2017
Proposed completionJun 2021
TodayJul 2026

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

63 units across 63 batches
BuildingFloorTypeArea sq mCount
A13 BHK971
A13 BHK931
A13 BHK891
A23 BHK971
A23 BHK931
A22 BHK651
A23 BHK891
A23 BHK951
A33 BHK971
A33 BHK931
A32 BHK651
A33 BHK891
A33 BHK951
A43 BHK971
A43 BHK931
A42 BHK651
A43 BHK891
A43 BHK951
A53 BHK971
A53 BHK931
A52 BHK651
A53 BHK891
A53 BHK951
A63 BHK971
A63 BHK931
A62 BHK651
A63 BHK891
A63 BHK951
A73 BHK971
A73 BHK931
A72 BHK651
B13 BHK971
B13 BHK931
B13 BHK891
B23 BHK951
B23 BHK891
B22 BHK651
B23 BHK931
B23 BHK971
B33 BHK951
B33 BHK891
B32 BHK651
B33 BHK931
B33 BHK971
B43 BHK951
B43 BHK891
B42 BHK651
B43 BHK931
B43 BHK971
B53 BHK951
B53 BHK891
B52 BHK651
B53 BHK931
B53 BHK971
B63 BHK951
B63 BHK891
B62 BHK651
B63 BHK931
B63 BHK971
B73 BHK891
B72 BHK651
B73 BHK931
B73 BHK971

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

UP-RERA · Promoter registration

ALLIANCE BUILD MORE PRIVATE LIMITED

CompanyPromoter type
1Registered projects
1Projects
1City
2017–2021Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

UP-RERA · Registration filing
District
Kanpur Nagar
Tehsil
Kanpur
Site access
E/PG-2 SCHEME NO - 3, AMBEDKAR PURAM, PANKI KALYANPUR ROAD, KALYANPUR, KANPUR
What’s nearby
SchoolsNo schools within 2km
HealthcareNo hospital within 5km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 1.4 kmRailway line 3.7 kmRailway station 4.3km away (Mohanlalganj)Limited bus connectivity nearby
Water & environment
Water body 526 mCanal 3.3 km
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹40.00 Cr declared to build 63 flats. What that works out to:

₹63.49 Lakhdeclared cost per flatall-in — land + construction

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

UP-RERA · Approved building plan
approved 13 Apr 2017 · 9 yrs ago
Building Permit no. 1020

The promised possession date (30 Jun 2021) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan 1020 on the approving authority’s portal to confirm the sanction.

Complaints register

1 complaint on UP-RERA’s register for this project.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — UP-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.