HORIZONMarkets
01

Complete project overview

RERA Telangana · Registration filing
Units
20 units
Unit mix
20 × Office Space
Saleable area
4831–7053 sq mper unit, as filed
Floors
20
Land area
16,390 sq m
Built-up area
1,11,938 sq m
Road widening
290 sq mland set aside for road widening

Timeline

RERA approvedNov 2020
Proposed completionDec 2024
TodayJul 2026
Construction progress

19% overall, as filed

Podiums0%
Stilt floor0%
Internal finishes0%
Flat fit-out0%
External finishes0%
OC-readiness0%
Stairs & lifts5%
Superstructure25%
Basement & plinth60%
Excavation100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

20 of 20 available
BuildingFloorTypeArea sq mAvailable
LSR TUDOR VANTAGE1Office Spacemortgaged4,8311 of 1
LSR TUDOR VANTAGE2Office Spacemortgaged5,2691 of 1
LSR TUDOR VANTAGE3Office Spacemortgaged6,0811 of 1
LSR TUDOR VANTAGE4Office Spacemortgaged6,7241 of 1
LSR TUDOR VANTAGE5Office Space6,7241 of 1
LSR TUDOR VANTAGE6Office Space6,1171 of 1
LSR TUDOR VANTAGE7Office Space6,7241 of 1
LSR TUDOR VANTAGE8Office Space6,7241 of 1
LSR TUDOR VANTAGE9Office Space6,7241 of 1
LSR TUDOR VANTAGE10Office Space6,1171 of 1
LSR TUDOR VANTAGE11Office Space6,7241 of 1
LSR TUDOR VANTAGE12Office Space6,7891 of 1
LSR TUDOR VANTAGE13Office Space6,8891 of 1
LSR TUDOR VANTAGE14Office Space6,2811 of 1
LSR TUDOR VANTAGE15Office Space6,8891 of 1
LSR TUDOR VANTAGE16Office Space6,8891 of 1
LSR TUDOR VANTAGE17Office Space6,8891 of 1
LSR TUDOR VANTAGE18Office Space6,3461 of 1
LSR TUDOR VANTAGE19Office Space7,0531 of 1
LSR TUDOR VANTAGE20Office Space5,0561 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

LSR TUDOR INFRA LLP

LLPPromoter type
Hyderabad, TelanganaBased in
1Projects
1City
2020–2024Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RERA Telangana · Registration filing
Locality
Kokapet
Village
koKapet
Mandal
Gandipet
District
Ranga Reddy
Pincode
500075
North boundary
Landin Syno256ofvattinagulapally and privateaccess
East boundary
Land in SyNo 88 of kokapet Village
South boundary
Land in SyNo 88 of kokpaet village
West boundary
45 M wide Road
What’s nearby
SchoolsNo schools within 2km · College or university 1.5km away
HealthcareNearest hospital 2.9km away
LifestyleNo parks within 2km · Gym or sports centre 1.4km away
ShoppingNo supermarket within 2km
Getting around
Primary road 889 mNo metro or railway within 5kmBus stop within 1km
Water & environment
Water body 1.3 km · Kokapet Lake
distances only — not a flood assessment
Government land classification

No residential (House Sites) class on record. The state classes this village’s land as Dry land, Agricultural Land fit for H.S., Land abutting NH/SH/ZPP/MPP. If it’s sold as residential plots, verify the layout’s conversion / approval.

Telangana Registration & Stamps
Declared external development
Roads0%
Water supply0%
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
Price analysisno declared cost on this filing — one government benchmark below

This state’s RERA filing carries no declared build cost at all — nothing to turn into a per-unit or per-sq-ft figure here. The one real, government-sourced number below is the closest thing to a benchmark this record can offer.

Government guidance value
₹27,000/sq ydresidential

₹32,292/sq m · effective May 2026 · apartments ₹2,700/sq ft, same source

The state’s minimum value for this locality’s land, set for stamp duty — a floor, not a market price. Source: Telangana Registration & Stamps.

04

Planning authority

RERA Telangana · Approved building plan

Hyderabad Metropolitan Development Authority (HMDA)

Urban Development Authority
Building Permit no. 036016/ZOA/C1/U6/HMDSurvey no. 88

The promised possession date (30 Dec 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan 036016/ZOA/C1/U6/HMD on the approving authority’s portal to confirm the sanction.

The approving body, at scale

HMDA

Urban Development Authority · Hyderabad metropolitan periphery

Has approved 3,643 RERA projectsabout 1 in 3 in Telangana.

an apartments market72% apartments · 28% plotted layouts. Apartments like yours are this body's core business.

Builders
2,462
On record
3,98,695 flats · 1,96,015 plots
Reach
71 mandals
Since
2016

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.