Complete project overview

HRERA Gurugram · Registration filing
Units
56 units
Parking
59 spaces
DTCP licence no.
11 of 2011the Haryana Town & Country Planning colony licence — verifiable on the DGTCP Haryana portal
Statutory approvals
8 declared obtained · Forest, Airport, Huda, Electrical, Environmentalclearances the promoter declared obtained at registration — not independently verified here

Timeline

Project startedMar 2012
RERA registeredFeb 2019
Proposed completionDec 2021
TodayJul 2026
Construction progress

58% overall, as filed

The % of external / site infrastructure (roads, water, sewerage, electrical) the promoter declared complete when this project was registered with HRERA — a snapshot at registration, and infrastructure, not building / tower construction. Not a live tracker.

Find your unit

Filed by type and size, in the batches the promoter registered — not a per-unit listing. Look yours up.

28 of 56 available
TypeArea sq mAvailable
BLOCK 7 (G+149)27921 of 25
BLOCK 8 (G+1)527 of 30
BLOCK 2 RESTAURANT (2ND FLOOR)1850 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system.

02

Builder’s track record

HRERA Gurugram · Promoter registration

Martial Buildcom Pvt.

CompanyPromoter type
Gurugram, HaryanaBased in
PARK · 1,260 units · completed 30 Nov 2021Prior registered project
1Projects
1City
2019–2021Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

HRERA Gurugram · Registration filing
Address
SECTOR-67, GURUGRAM
Tehsil
GURGAON
District
GURUGRAM
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 1.1km away · 1 clinic within 1km
LifestyleNo parks within 2km · 20+ restaurants and cafes within 1km
ShoppingSupermarket 700m away
Getting around
Expressway 794 m · Sohna RoadNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
Water body 487 m
distances only — not a flood assessment
Land, title & encumbrance
Land licencePromoter is the licence holder for the land
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
Price analysisdeclared build cost — not a sale price

₹134.96 Cr declared to build 56 flats. What that works out to:

₹2.41 Crdeclared cost per flatall-in — land + construction
₹14,378/sq ftof carpet area₹1,54,767/sq m
12%of the cost is land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

HRERA Gurugram · Approved building plan

Directorate of Town & Country Planning, Haryana (DTCP)

Town & Country Planning (DTCP)
Building Permit

The promised possession date (31 Dec 2021) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — HRERA Gurugram does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — HRERA Gurugram does not publish a complaints register. This read cannot speak to them either way.