HORIZONMarkets
01

Complete project overview

UP-RERA · Registration filing
Units
71 units
Unit mix
64 × 3 BHK · 7 × 2 BHK
Carpet area
71–98 sq mper unit, as filed
Floors
7
Land area
3,894 sq m

Timeline

Project startedDec 2019
RERA registeredJul 2021
Proposed completionSep 2024
TodayJul 2026

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

71 units across 35 batches
BuildingFloorTypeArea sq mCount
112 BHK711
113 BHK892
113 BHK875
113 BHK981
113 BHK871
122 BHK711
123 BHK892
123 BHK875
123 BHK981
123 BHK871
132 BHK711
133 BHK892
133 BHK875
133 BHK981
133 BHK871
142 BHK711
143 BHK892
143 BHK875
143 BHK981
143 BHK871
152 BHK711
153 BHK892
153 BHK875
153 BHK981
153 BHK871
162 BHK711
163 BHK892
163 BHK875
163 BHK981
163 BHK871
172 BHK711
173 BHK892
173 BHK875
173 BHK982
173 BHK871

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

UP-RERA · Promoter registration

BUOYANT BUILDTECH PVT LTD

CompanyPromoter type
1Registered projects
1Projects
1City
2021–2024Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

UP-RERA · Registration filing
District
Aligarh
Tehsil
Koil
What’s nearby
SchoolsNearest school 1.4km away
HealthcareHospital 259m away · Clinic within 2km
LifestylePark 1.3km away
ShoppingNo supermarket within 2km
Getting around
Expressway 125 m · Aligarh BypassPrimary road 1.5 kmRailway line 2.3 kmRailway station 2.7km away (Aligarh Junction)Limited bus connectivity nearby
Water & environment
Water body 718 m
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹29.85 Cr declared to build 71 flats. What that works out to:

₹42.04 Lakhdeclared cost per flatall-in — land + construction

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

UP-RERA · Approved building plan
approved 27 Sep 2019 · 6 yrs ago
Building Permit no. MAP20190330174114323

The promised possession date (26 Sep 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan MAP20190330174114323 on the approving authority’s portal to confirm the sanction.

Complaints register

None on record with UP-RERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — UP-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.