HORIZONMarkets
01

Complete project overview

RERA Telangana · Registration filing
Units
20 units
Unit mix
20 × 2BHK
Saleable area
90 sq mper unit, as filed
Floors
5
Land area
697 sq m
Built-up area
1,797 sq m

Timeline

RERA approvedMay 2020
Proposed completionMay 2026
TodayJul 2026
Construction progress

15.6% overall, as filed

Podiums0%
Stilt floor0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Superstructure6%
Basement & plinth50%
Excavation100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

20 of 20 available
BuildingFloorTypeArea sq mAvailable
MAGNUS12BHKmortgaged903 of 3
MAGNUS12BHK901 of 1
MAGNUS22BHK903 of 3
MAGNUS22BHKmortgaged901 of 1
MAGNUS32BHK904 of 4
MAGNUS42BHK904 of 4
MAGNUS52BHK904 of 4

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

Sri Dhanvi Infra

PartnershipPromoter type
Hyderabad, TelanganaBased in
8Projects
2Cities
2018–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
2,336 homeson the public record across 8 projects
29,068 sq mbuilt-up filed
14,884 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Hyderabad Metropolitan Development Authority (HMDA)Urban Development Authoritythis project6 of 7 projects
Directorate of Town & Country Planning (DTCP)Town & Country Planning (DTCP)1 of 7 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RERA Telangana · Registration filing
Locality
ALKAPURI TOWN SHIP
Village
Neknapur
Mandal
Gandipet
District
Ranga Reddy
Pincode
500089
North boundary
PLOT NO 4
East boundary
40 FEET ROAD
South boundary
PLOT NO 1
West boundary
PLOT NO 8 AND 9
What’s nearby
Schools1 school within 1km · College or university 2.0km away
HealthcareHospital 224m away · 2 clinics within 1km · Pharmacy within 1km
LifestylePark 1.5km away · Gym or sports centre 329m away · 4 restaurants and cafes within 1km
ShoppingSupermarket 237m away · Bank 417m away
Getting around
Expressway 3.7 kmPrimary road 2.0 km · Old Bombay HighwayMetro station 4.5km away (Peddamma Gudi)Limited bus connectivity nearby
Water & environment
Water body 1.4 km · Pedda Cheruvu
distances only — not a flood assessment
Government land classification

No residential (House Sites) class on record. The state classes this village’s land as Dry land, Land abutting NH/SH/ZPP/MPP, Agricultural Land fit for H.S.. If it’s sold as residential plots, verify the layout’s conversion / approval.

Telangana Registration & Stamps
Declared external development
Roads0%
Water supply0%
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
Price analysisno declared cost on this filing — one government benchmark below

This state’s RERA filing carries no declared build cost at all — nothing to turn into a per-unit or per-sq-ft figure here. The one real, government-sourced number below is the closest thing to a benchmark this record can offer.

Government guidance value
₹23,700/sq ydresidential

₹28,345/sq m · effective May 2026 · apartments ₹2,700/sq ft, same source

The state’s minimum value for this locality’s land, set for stamp duty — a floor, not a market price. Source: Telangana Registration & Stamps.

04

Planning authority

RERA Telangana · Approved building plan

Hyderabad Metropolitan Development Authority (HMDA)

Urban Development Authority
Building Permit
Survey no. 78

The promised possession date (6 May 2026) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

HMDA

Urban Development Authority · Hyderabad metropolitan periphery

Has approved 3,643 RERA projectsabout 1 in 3 in Telangana.

an apartments market72% apartments · 28% plotted layouts. Apartments like yours are this body's core business.

Builders
2,462
On record
3,98,695 flats · 1,96,015 plots
Reach
71 mandals
Since
2016

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.