Complete project overview
RAJ-RERA · Registration filing- Land area
- 1,358 sq m
- Completion deadline extended
- 1 extension on record — latest to 15 Jun 2020declared reason: other than force majeure
- Description
- 1 The approval for our project has been granted by the UIT Udaipur vide letter no 1105 dated 02-04-2012 for stilt Floor+Gf+first to second floor. Further, UIT Udaipur has granted permission for 3 to 6 floor and additional two floor (i.e. 7 & 8 floor) vide letter no 3146 dated 05/10/2012. The approved maps have been released by UIT Udaipur for upto 6th floor and as 7th and 8th floor are similar to 6th floor the maps have not been released by UIT Udaipur. The clarification lettrr regarding this has also been uploaded along with approved maps. As per remark the correct phase area has been rectified in Land Details of Registering Project.
Timeline
Builder’s track record
RAJ-RERA · Promoter registrationRAM SURESH YADAV
The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
Location & price analysis
RAJ-RERA · Registration filing- Address
- 17-18, BHUWANA, GIRWA, UDAIPUR, RAJASTHAN, BHUWANA, BHUWANA, Girwa, Udaipur, 313001
- Village
- BHUWANA
- Taluka
- Girwa
- District
- Udaipur
- Pincode
- 313001
₹12.55 Cr declared. What that works out to:
This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.
Planning authority
RAJ-RERA · Approved building planThe promised possession date (31 Dec 2019) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.
A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.
What this record cannot tell you
- Build quality — no filing records how well it was actually built.
- Private disputes — only complaints escalated to the authority appear here.
- What it will be worth — the record is the past; it does not price the future.
- Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
- Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.