Complete project overview

RAJ-RERA · Registration filing
Units
1,089 units
Mix
612 × LIG-2BHK (G +7 Floor) · 210 × EWS-1BHK (1 to 7Floor) · 210 × LIG-2BHK (1 to 7Floor) · 30 × EWS-1BHK (GF) · 12 × LIG-2BHK (GF) · 8 × Shop no. S1 TO S8 (GF)
Carpet area
24–42 sq mper-type range, as filed
Land area
16,920 sq m
Completion deadline extended
4 extensions on record — latest to 3 May 2025declared reason: force majeure
Description
The following details have been submitted by the developers: After receiving the Environmental NOC the revised maps have been approvedby JDA. The details of previous approved & revised approval is as follows: Block -A Previously approved maps(G+3+Mumty) Revised approved maps(G+4+Mumty) LIG Apartments 300 378 Car Parking 5 5 Two Wheeler Parking 1224 1224 Commercial 162.08 Sq. Mtr. 326.82 Sq. Mtr. Block -B Previously approved maps(G+Mumty) Revised approved maps (G+4+Mumty) LIG Apartments 0 144 EWS Apartments 66 150 Car Parking 3 3 Two Wheeler Parking 612 708 Commercial 102.95 Sq. Mtr. 120.85 Sq. Mtr. The maps approved on Dated 02.05.2017 Have been attetched with approved letter under copy of layout approval and building plan approval. The Revised maps approved on Dated 01.12.2017 Have been attetched with approved letter under Other approval as may be required and obtained for the project. The above mentioned details are being added on 04.01.2018. Above changes in web portel on dated - 12.09.2019

Timeline

Construction startMay 2017
RERA registeredSep 2017
Proposed completionMay 2021
TodayJul 2026

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

1,089 units across 7 batches
BuildingTypeArea sq mCount
MANORAMA HEIGHTSEWS-1BHK (1 to 7Floor)24210
MANORAMA HEIGHTSLIG-2BHK (1 to 7Floor)40210
MANORAMA HEIGHTSLIG-2BHK (G +7 Floor)40612
MANORAMA HEIGHTSEWS-1BHK (GF)2430
MANORAMA HEIGHTSLIG-2BHK (GF)4012
MANORAMA HEIGHTSShop no. S1 TO S7427
MANORAMA HEIGHTSShop no. S1 TO S8 (GF)428

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

RAJ-RERA · Promoter registration

SHRI HARI GROUP

OrganisationPromoter type
Jaipur, RajasthanBased in
1Projects
1City
2017–2021Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
126,127/1,128,129,131, Rampura Road, Narottampura, Sanganer, Jaipur, 302029
Village
Narottampura
Taluka
Sanganer
District
Jaipur
Pincode
302029
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 2.9km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 4.0 km · Jaipur Kishangarh ExpresswayNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
Canal 3.1 kmWater body 3.9 km · Nevta Lake
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹105.84 Cr declared to build 1,089 flats. What that works out to:

₹9.72 Lakhdeclared cost per flatall-in — land + construction
₹1,847/sq ftof built-up area₹19,883/sq m
26%of the cost is land₹1,528/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RAJ-RERA · Approved building plan
Building Permitapproved 5 Sep 2017 · 8 yrs ago

The promised possession date (3 May 2021) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.