Complete project overview
RAJ-RERA · Registration filing- Land area
- 21,050 sq m
- Completion deadline extended
- 5 extensions on record — latest to 19 Feb 2026
- Description
- The maps for the project have been sanctioned for mixed use development and the project is divided into two parts Hotel and Residential Block. As the Hotel and Residential block are segregated in all aspects and we wish to sell only the residential block we have mentioned the details of Residential block and applied for registration of the Residential block . The project is divided into two parts wherein 686 car parking and 978 two wheeler parking have been sanctioned in totality out of which 249 car parking and 249 two wheeler parking and 86 car parking and 84 two wheeler parking for visitors pertain to residential project being registered and remaining shall rest for other part i.e. hotel. The detail of separate bank account as per section 4(2)(l)(D) of the Act has been changed on 18.06.2019. As per this modification the earlier account no. 37668158352 of State Bank of India Bank has now been changed to account no.38458395790 of State Bank of India Bank.
Timeline
Builder’s track record
RAJ-RERA · Promoter registrationJAIPUR MOTELS AND BUILDESTATES PRIVATE LIMITED
The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
Location & price analysis
RAJ-RERA · Registration filing- Address
- 776/1/1,777,778/1,778/2,778/3,779/1,779/2,779/3,786/1/1,776/1,776/2,786/1,786/2, Sawai Getor, Sanganer, Jaipur, 302017
- Taluka
- Sanganer
- District
- Jaipur
- Pincode
- 302017
₹181.83 Cr declared. What that works out to:
This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.
Planning authority
RAJ-RERA · Approved building planThe promised possession date (18 Aug 2022) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.
A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.
What this record cannot tell you
- Build quality — no filing records how well it was actually built.
- Private disputes — only complaints escalated to the authority appear here.
- What it will be worth — the record is the past; it does not price the future.
- Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
- Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.