Complete project overview

RERA Telangana · Registration filing
Units
53 units
Unit mix
53 × 3BHK
Saleable area
158–189 sq mper unit, as filed
Floors
8
Land area
4,114 sq m
Built-up area
9,541 sq m
Road widening
720 sq mland set aside for road widening

Timeline

RERA approvedMay 2024
Proposed completionMay 2029
TodayJul 2026
Construction progress

72.5% overall, as filed

Podiums0%
OC-readiness45%
External finishes55%
Flat fit-out65%
Stairs & lifts80%
Internal finishes85%
Stilt floor95%
Excavation100%
Basement & plinth100%
Superstructure100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

42 of 53 available
BuildingFloorTypeArea sq mAvailable
MANVITHAs VISTARA13BHKmortgaged1642 of 2
MANVITHAs VISTARA13BHKmortgaged1582 of 2
MANVITHAs VISTARA23BHK1892 of 3
MANVITHAs VISTARA23BHKmortgaged1811 of 1
MANVITHAs VISTARA23BHKmortgaged1773 of 3
MANVITHAs VISTARA33BHK1893 of 3
MANVITHAs VISTARA33BHK1811 of 1
MANVITHAs VISTARA33BHK1772 of 3
MANVITHAs VISTARA43BHK1892 of 3
MANVITHAs VISTARA43BHK1811 of 1
MANVITHAs VISTARA43BHK1772 of 3
MANVITHAs VISTARA53BHK1773 of 3
MANVITHAs VISTARA53BHK1891 of 3
MANVITHAs VISTARA53BHK1810 of 1
MANVITHAs VISTARA63BHK1893 of 3
MANVITHAs VISTARA63BHK1811 of 1
MANVITHAs VISTARA63BHK1772 of 3
MANVITHAs VISTARA73BHK1893 of 3
MANVITHAs VISTARA73BHK1772 of 3
MANVITHAs VISTARA73BHK1811 of 1
MANVITHAs VISTARA83BHK1893 of 3
MANVITHAs VISTARA83BHK1772 of 3
MANVITHAs VISTARA83BHK1810 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

MANVITHA INFRA PROJECTS

PartnershipPromoter type
Ranga Reddy, TelanganaBased in
1Projects
1City
2024–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
Gajularamaram
Mandal
Qutballapur
District
Medchal-Malkajgiri
Pincode
500055
North boundary
Land in Sy No 117 Part
East boundary
40 Feet Wide Road
South boundary
Land in Sy No 140 Part
West boundary
Land in Sy No 139 Part
What’s nearby
SchoolsNearest school 2.0km away · College or university 1.8km away
HealthcareHospital 1.9km away · Clinic within 2km
LifestylePark 1.6km away · Gym or sports centre 1.2km away
ShoppingSupermarket 1.0km away · Mall 1.1km away
Getting around
Expressway 4.3 km · Nizampet - JNTU Road Mumbai HighwayPrimary road 865 m · Medak RoadMetro station 4.3km away (JNTU College)Limited bus connectivity nearby
Water & environment
Water body 564 m
distances only — not a flood assessment
Declared external development
Water supply100%
Electricity40%
Roads0%
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Greater Hyderabad Municipal Corporation (GHMC)

Municipal / Corporation
Building Permit
Survey no. 117 PART
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

GHMC

Municipal Corporation · Hyderabad city core

Has approved 3,102 RERA projectsabout 1 in 4 in Telangana.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,994
On record
2,20,211 flats · 3,387 plots
Reach
65 mandals
Since
2016

More apartment-heavy than Telangana overall — 99% apartments here vs 66% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.