HORIZONMarkets
01

Complete project overview

RERA Telangana · Registration filing
Units
34 units
Unit mix
21 × 3BHK, 13 × 2BHK
Saleable area
106–141 sq mper unit, as filed
Floors
6
Land area
1,973 sq m
Built-up area
93,450 sq m
Road widening
488 sq mland set aside for road widening

Timeline

RERA approvedJul 2021
Proposed completionJul 2027
TodayJul 2026
Construction progress

88.6% overall, as filed

Podiums0%
Flat fit-out90%
External finishes96%
Excavation100%
Basement & plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Stairs & lifts100%
OC-readiness100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

34 of 34 available
BuildingFloorTypeArea sq mAvailable
MARIAMS KATAM GANESH ARCADE13BHK1411 of 1
MARIAMS KATAM GANESH ARCADE12BHK1081 of 1
MARIAMS KATAM GANESH ARCADE13BHK1272 of 2
MARIAMS KATAM GANESH ARCADE12BHK1061 of 1
MARIAMS KATAM GANESH ARCADE23BHK1412 of 2
MARIAMS KATAM GANESH ARCADE22BHK1081 of 1
MARIAMS KATAM GANESH ARCADE23BHK1272 of 2
MARIAMS KATAM GANESH ARCADE22BHK1061 of 1
MARIAMS KATAM GANESH ARCADE33BHKmortgaged1412 of 2
MARIAMS KATAM GANESH ARCADE32BHK1081 of 1
MARIAMS KATAM GANESH ARCADE33BHKmortgaged1272 of 2
MARIAMS KATAM GANESH ARCADE32BHK1061 of 1
MARIAMS KATAM GANESH ARCADE43BHK1412 of 2
MARIAMS KATAM GANESH ARCADE42BHK1081 of 1
MARIAMS KATAM GANESH ARCADE42BHK1272 of 2
MARIAMS KATAM GANESH ARCADE42BHK1061 of 1
MARIAMS KATAM GANESH ARCADE53BHK1412 of 2
MARIAMS KATAM GANESH ARCADE52BHK1081 of 1
MARIAMS KATAM GANESH ARCADE53BHK1272 of 2
MARIAMS KATAM GANESH ARCADE52BHK1061 of 1
MARIAMS KATAM GANESH ARCADE63BHK1412 of 2
MARIAMS KATAM GANESH ARCADE62BHK1081 of 1
MARIAMS KATAM GANESH ARCADE63BHK1272 of 2

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

MARAM INFRA PROJECTS PRIVATE LIMITED

CompanyPromoter type
Hyderabad, TelanganaBased in
7Projects
3Cities
2019–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
1,032 homeson the public record across 7 projects
2,26,801 sq mbuilt-up filed
46,955 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Greater Hyderabad Municipal Corporation (GHMC)Municipal / Corporation3 of 5 projects
Hyderabad Metropolitan Development Authority (HMDA)Urban Development Authority2 of 5 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RERA Telangana · Registration filing
Locality
JILLELGUDA
Village
Karmanghat
Mandal
Saroornagar
District
Ranga Reddy
Pincode
500079
North boundary
PARAVATHAMMA ENCLAVE
East boundary
ROAD WIDTH 12
South boundary
ROAD WIDTH 9
West boundary
EXISTING BUILDING
What’s nearby
SchoolsNo schools within 2km · College or university 1.9km away
HealthcareHospital 392m away · 1 clinic within 1km · Pharmacy within 1km
LifestylePark 789m away · Swimming pool within 2km
ShoppingSupermarket 1.6km away · Mall 1.9km away · Bank 803m away
Getting around
Expressway 412 m · Inner Ring RoadPrimary road 337 m · Bairamalguda RoadRailway line 4.0 km · chaitanyapuri metroMetro station 2.0km away (L. B. Nagar Metro Station)Bus stop within 1km
Water & environment
Water body 1.3 km
distances only — not a flood assessment
Declared external development
Water supply64%
Sewerage (Chamber,…59%
Green Strip/TOT LO…35%
Rainwater22%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
Roads0%
Street lighting0%
Community Building…0%
Sewage0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
Price analysisno declared cost on this filing — one government benchmark below

This state’s RERA filing carries no declared build cost at all — nothing to turn into a per-unit or per-sq-ft figure here. The one real, government-sourced number below is the closest thing to a benchmark this record can offer.

Government guidance value
₹25,200/sq ydresidential

₹30,139/sq m · effective May 2026 · apartments ₹3,000/sq ft, same source

The state’s minimum value for this locality’s land, set for stamp duty — a floor, not a market price. Source: Telangana Registration & Stamps.

04

Planning authority

RERA Telangana · Approved building plan
Building Permit
Survey no. 59/Q/AA, 59/P, 59/Q/A
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.