HORIZONMarkets
01

Complete project overview

RERA Telangana · Registration filing
Units
533 units
Unit mix
318 × 3BHK, 118 × 2BHK, 64 × 4BHK, 32 × 5BHK, 1 × Ground
Saleable area
129–3217 sq mper unit, as filed
Floors
32
Buildings
3
Land area
16,870 sq m
Built-up area
1,09,964 sq m

Timeline

RERA approvedJan 2022
Proposed completionJan 2028
TodayJul 2026
Construction progress

30% overall, as filed

Stilt floor0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Excavation100%
Basement & plinth100%
Podiums100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

410 of 533 available
BuildingFloorTypeArea sq mAvailable
AMENITIES BLOCK1Ground3,2171 of 1
BLOCK-A15BHKmortgaged1461 of 1
BLOCK-A12BHKmortgaged1292 of 2
BLOCK-A13BHKmortgaged1672 of 2
BLOCK-A13BHKmortgaged1951 of 1
BLOCK-A13BHKmortgaged1951 of 1
BLOCK-A13BHKmortgaged2291 of 1
BLOCK-A13BHKmortgaged2121 of 1
BLOCK-A23BHKmortgaged1672 of 2
BLOCK-A25BHKmortgaged1461 of 1
BLOCK-A23BHKmortgaged1952 of 2
BLOCK-A23BHKmortgaged2291 of 1
BLOCK-A23BHKmortgaged2121 of 1
BLOCK-A22BHKmortgaged1292 of 2
BLOCK-A33BHKmortgaged1672 of 2
BLOCK-A35BHKmortgaged1461 of 1
BLOCK-A33BHKmortgaged1952 of 2
BLOCK-A33BHKmortgaged2291 of 1
BLOCK-A33BHKmortgaged1291 of 1
BLOCK-A32BHKmortgaged1291 of 1
BLOCK-A33BHKmortgaged2121 of 1
BLOCK-A43BHKmortgaged1672 of 2
BLOCK-A45BHKmortgaged1461 of 1
BLOCK-A43BHKmortgaged1952 of 2
BLOCK-A43BHKmortgaged2291 of 1
BLOCK-A43BHKmortgaged2121 of 1
BLOCK-A42BHKmortgaged1292 of 2
BLOCK-A53BHKmortgaged1672 of 2
BLOCK-A55BHKmortgaged1461 of 1
BLOCK-A53BHKmortgaged1952 of 2
BLOCK-A52BHK1290 of 2
BLOCK-A53BHK2121 of 1
BLOCK-A53BHKmortgaged2291 of 1
BLOCK-A63BHK1670 of 2
BLOCK-A63BHK1952 of 2
BLOCK-A63BHK2291 of 1
BLOCK-A62BHK1290 of 2
BLOCK-A63BHK2120 of 1
BLOCK-A65BHK1460 of 1
BLOCK-A73BHK1670 of 2
BLOCK-A75BHK1460 of 1
BLOCK-A73BHK1952 of 2
BLOCK-A73BHK2291 of 1
BLOCK-A73BHK2121 of 1
BLOCK-A72BHK1292 of 2
BLOCK-A83BHK1951 of 2
BLOCK-A82BHK1292 of 2
BLOCK-A83BHK1670 of 2
BLOCK-A85BHK1460 of 1
BLOCK-A83BHK2120 of 1
BLOCK-A83BHK2290 of 1
BLOCK-A93BHK1951 of 2
BLOCK-A92BHK1291 of 2
BLOCK-A93BHK1670 of 2
BLOCK-A93BHK2290 of 1
BLOCK-A93BHK2120 of 1
BLOCK-A95BHK1461 of 1
BLOCK-A103BHK1671 of 2
BLOCK-A103BHK1952 of 2
BLOCK-A105BHK1461 of 1
BLOCK-A102BHK1290 of 2
BLOCK-A103BHK2120 of 1
BLOCK-A103BHK2290 of 1
BLOCK-A115BHK1461 of 1
BLOCK-A113BHK1672 of 2
BLOCK-A113BHK1951 of 2
BLOCK-A112BHK1290 of 2
BLOCK-A113BHK2290 of 1
BLOCK-A113BHK2120 of 1
BLOCK-A123BHK1672 of 2
BLOCK-A123BHK1952 of 2
BLOCK-A125BHK1460 of 1
BLOCK-A123BHK2120 of 1
BLOCK-A123BHK2290 of 1
BLOCK-A122BHK1290 of 1
BLOCK-A133BHK1671 of 2
BLOCK-A133BHK1952 of 2
BLOCK-A132BHK1291 of 1
BLOCK-A135BHK1461 of 1
BLOCK-A133BHK2290 of 1
BLOCK-A133BHK2120 of 1
BLOCK-A143BHK1952 of 2
BLOCK-A142BHK1292 of 2
BLOCK-A143BHK2120 of 1
BLOCK-A143BHK1670 of 2
BLOCK-A143BHK2290 of 1
BLOCK-A145BHK1461 of 1
BLOCK-A153BHK1672 of 2
BLOCK-A153BHK1952 of 2
BLOCK-A153BHK2291 of 1
BLOCK-A153BHK2121 of 1
BLOCK-A152BHK1292 of 2
BLOCK-A155BHK1460 of 1
BLOCK-A165BHK1461 of 1
BLOCK-A163BHK1952 of 2
BLOCK-A163BHK2291 of 1
BLOCK-A163BHK2131 of 1
BLOCK-A162BHK1292 of 2
BLOCK-A163BHK1670 of 2
BLOCK-A175BHK1461 of 1
BLOCK-A173BHK1671 of 2
BLOCK-A173BHK1952 of 2
BLOCK-A173BHK2121 of 1
BLOCK-A172BHK1292 of 2
BLOCK-A173BHK2290 of 1
BLOCK-A183BHK1671 of 2
BLOCK-A183BHK1952 of 2
BLOCK-A183BHK2291 of 1
BLOCK-A183BHK2121 of 1
BLOCK-A185BHK1460 of 1
BLOCK-A193BHK1671 of 2
BLOCK-A195BHK1461 of 1
BLOCK-A193BHK1952 of 2
BLOCK-A193BHK2291 of 1
BLOCK-A193BHK2121 of 1
BLOCK-A192BHK1291 of 2
BLOCK-A203BHK1672 of 2
BLOCK-A205BHK1461 of 1
BLOCK-A203BHK1951 of 1
BLOCK-A203BHK2291 of 1
BLOCK-A203BHK2121 of 1
BLOCK-A202BHK1291 of 2
BLOCK-A215BHK1461 of 1
BLOCK-A213BHK1671 of 2
BLOCK-A213BHK1952 of 2
BLOCK-A213BHK2291 of 1
BLOCK-A213BHK2121 of 1
BLOCK-A212BHK1292 of 2
BLOCK-A225BHK1461 of 1
BLOCK-A223BHK1952 of 2
BLOCK-A223BHK2291 of 1
BLOCK-A223BHK2121 of 1
BLOCK-A222BHK1292 of 2
BLOCK-A223BHK1670 of 2
BLOCK-A235BHK1461 of 1
BLOCK-A233BHK1671 of 2
BLOCK-A233BHK1952 of 2
BLOCK-A233BHK2291 of 1
BLOCK-A232BHK1291 of 2
BLOCK-A233BHK2120 of 1
BLOCK-A245BHK1461 of 1
BLOCK-A243BHK1952 of 2
BLOCK-A243BHK2121 of 1
BLOCK-A242BHK1292 of 2
BLOCK-A243BHK2291 of 1
BLOCK-A243BHK1670 of 1
BLOCK-A253BHK1671 of 2
BLOCK-A255BHK1461 of 1
BLOCK-A253BHK1952 of 2
BLOCK-A253BHK2291 of 1
BLOCK-A253BHK2121 of 1
BLOCK-A252BHK1292 of 2
BLOCK-A263BHK1671 of 2
BLOCK-A265BHK1461 of 1
BLOCK-A263BHK1952 of 2
BLOCK-A263BHK2291 of 1
BLOCK-A263BHK2121 of 1
BLOCK-A262BHK1292 of 2
BLOCK-A273BHK1672 of 2
BLOCK-A275BHK1461 of 1
BLOCK-A273BHK1952 of 2
BLOCK-A273BHK2121 of 1
BLOCK-A272BHK1292 of 2
BLOCK-A273BHK2290 of 1
BLOCK-A283BHK1672 of 2
BLOCK-A285BHK1461 of 1
BLOCK-A283BHK1952 of 2
BLOCK-A283BHK2291 of 1
BLOCK-A283BHK2121 of 1
BLOCK-A292BHK1292 of 2
BLOCK-A293BHK1672 of 2
BLOCK-A295BHK1461 of 1
BLOCK-A293BHK1952 of 2
BLOCK-A293BHK2291 of 1
BLOCK-A293BHK2120 of 1
BLOCK-A303BHK1672 of 2
BLOCK-A305BHK1461 of 1
BLOCK-A303BHK1952 of 2
BLOCK-A303BHK2291 of 1
BLOCK-A303BHK2121 of 1
BLOCK-A302BHK1292 of 2
BLOCK-A313BHK1672 of 2
BLOCK-A315BHK1461 of 1
BLOCK-A313BHK1952 of 2
BLOCK-A313BHK2291 of 1
BLOCK-A312BHK1292 of 2
BLOCK-A313BHK2120 of 1
BLOCK-A323BHK1672 of 2
BLOCK-A325BHK1461 of 1
BLOCK-A323BHK1952 of 2
BLOCK-A323BHK2291 of 1
BLOCK-A323BHK2121 of 1
BLOCK-A322BHK1292 of 2
BLOCK-B13BHKmortgaged2121 of 1
BLOCK-B12BHKmortgaged1292 of 2
BLOCK-B14BHKmortgaged3322 of 2
BLOCK-B13BHKmortgaged1952 of 2
BLOCK-B13BHKmortgaged2291 of 1
BLOCK-B24BHKmortgaged3322 of 2
BLOCK-B23BHKmortgaged1952 of 2
BLOCK-B23BHKmortgaged2291 of 1
BLOCK-B23BHKmortgaged2121 of 1
BLOCK-B22BHKmortgaged1292 of 2
BLOCK-B34BHKmortgaged3322 of 2
BLOCK-B34BHKmortgaged1951 of 1
BLOCK-B33BHKmortgaged1951 of 1
BLOCK-B33BHKmortgaged2291 of 1
BLOCK-B33BHKmortgaged2121 of 1
BLOCK-B32BHKmortgaged1292 of 2
BLOCK-B44BHKmortgaged3322 of 2
BLOCK-B43BHKmortgaged1952 of 2
BLOCK-B43BHKmortgaged2291 of 1
BLOCK-B43BHKmortgaged2121 of 1
BLOCK-B42BHKmortgaged1292 of 2
BLOCK-B52BHK1290 of 2
BLOCK-B53BHK1952 of 2
BLOCK-B54BHK3322 of 2
BLOCK-B53BHK2291 of 1
BLOCK-B53BHK2121 of 1
BLOCK-B64BHK3321 of 2
BLOCK-B63BHK2291 of 1
BLOCK-B63BHK2121 of 1
BLOCK-B62BHK1291 of 2
BLOCK-B63BHK1950 of 2
BLOCK-B74BHK3322 of 2
BLOCK-B73BHK2291 of 1
BLOCK-B72BHK1292 of 2
BLOCK-B73BHK1950 of 2
BLOCK-B73BHK2120 of 1
BLOCK-B83BHK1951 of 2
BLOCK-B83BHK2291 of 1
BLOCK-B83BHK2121 of 1
BLOCK-B82BHK1290 of 2
BLOCK-B84BHK3322 of 2
BLOCK-B94BHK3322 of 2
BLOCK-B93BHK1951 of 2
BLOCK-B93BHK2291 of 1
BLOCK-B92BHK1292 of 2
BLOCK-B93BHK2120 of 1
BLOCK-B102BHK1291 of 2
BLOCK-B104BHK3321 of 2
BLOCK-B103BHK1951 of 2
BLOCK-B103BHK2291 of 1
BLOCK-B103BHK2120 of 1
BLOCK-B114BHK3321 of 2
BLOCK-B113BHK1952 of 2
BLOCK-B113BHK2291 of 1
BLOCK-B112BHK1290 of 2
BLOCK-B113BHK2120 of 1
BLOCK-B124BHK3322 of 2
BLOCK-B123BHK2291 of 1
BLOCK-B122BHK1291 of 2
BLOCK-B123BHK1950 of 2
BLOCK-B123BHK2120 of 1
BLOCK-B134BHK3322 of 2
BLOCK-B133BHK1951 of 2
BLOCK-B133BHK2291 of 1
BLOCK-B133BHK2121 of 1
BLOCK-B132BHK1290 of 2
BLOCK-B144BHK3322 of 2
BLOCK-B143BHK1952 of 2
BLOCK-B143BHK2291 of 1
BLOCK-B143BHK2121 of 1
BLOCK-B142BHK1291 of 2
BLOCK-B154BHK3321 of 2
BLOCK-B153BHK1952 of 2
BLOCK-B153BHK2121 of 1
BLOCK-B152BHK1291 of 2
BLOCK-B153BHK2290 of 1
BLOCK-B164BHK3322 of 2
BLOCK-B163BHK1952 of 2
BLOCK-B162BHK1291 of 2
BLOCK-B163BHK2120 of 1
BLOCK-B163BHK2290 of 1
BLOCK-B174BHK3322 of 2
BLOCK-B173BHK1951 of 2
BLOCK-B173BHK2291 of 1
BLOCK-B172BHK1291 of 2
BLOCK-B173BHK2120 of 1
BLOCK-B184BHK3321 of 1
BLOCK-B182BHK3321 of 1
BLOCK-B183BHK1951 of 2
BLOCK-B183BHK2120 of 1
BLOCK-B183BHK2290 of 1
BLOCK-B194BHK3322 of 2
BLOCK-B193BHK1952 of 2
BLOCK-B193BHK2291 of 1
BLOCK-B193BHK2121 of 1
BLOCK-B192BHK1290 of 2
BLOCK-B204BHK3322 of 2
BLOCK-B203BHK1951 of 1
BLOCK-B203BHK2291 of 1
BLOCK-B202BHK1292 of 2
BLOCK-B203BHK01 of 1
BLOCK-B203BHK2120 of 1
BLOCK-B214BHK3321 of 2
BLOCK-B213BHK1952 of 2
BLOCK-B213BHK2291 of 1
BLOCK-B213BHK2121 of 1
BLOCK-B212BHK1290 of 2
BLOCK-B224BHK3322 of 2
BLOCK-B223BHK1952 of 2
BLOCK-B223BHK2291 of 1
BLOCK-B223BHK2121 of 1
BLOCK-B222BHK1291 of 2
BLOCK-B234BHK3322 of 2
BLOCK-B233BHK1952 of 2
BLOCK-B233BHK2291 of 1
BLOCK-B233BHK2121 of 1
BLOCK-B232BHK1292 of 2
BLOCK-B244BHK3322 of 2
BLOCK-B243BHK1952 of 2
BLOCK-B243BHK2291 of 1
BLOCK-B242BHK1291 of 2
BLOCK-B243BHK2120 of 1
BLOCK-B254BHK3322 of 2
BLOCK-B253BHK1952 of 2
BLOCK-B253BHK2291 of 1
BLOCK-B253BHK2121 of 1
BLOCK-B252BHK1291 of 2
BLOCK-B264BHK3322 of 2
BLOCK-B263BHK1952 of 2
BLOCK-B263BHK2291 of 1
BLOCK-B263BHK2121 of 1
BLOCK-B262BHK1292 of 2
BLOCK-B274BHK3321 of 2
BLOCK-B273BHK1952 of 2
BLOCK-B273BHK2291 of 1
BLOCK-B273BHK2121 of 1
BLOCK-B272BHK1292 of 2
BLOCK-B284BHK3321 of 2
BLOCK-B283BHK1952 of 2
BLOCK-B283BHK2291 of 1
BLOCK-B283BHK2120 of 1
BLOCK-B294BHK3322 of 2
BLOCK-B293BHK1952 of 2
BLOCK-B293BHK2291 of 1
BLOCK-B293BHK2121 of 1
BLOCK-B292BHK1292 of 2
BLOCK-B304BHK3321 of 2
BLOCK-B303BHK1952 of 2
BLOCK-B303BHK2291 of 1
BLOCK-B303BHK2121 of 1
BLOCK-B302BHK1292 of 2
BLOCK-B314BHK3321 of 2
BLOCK-B313BHK1952 of 2
BLOCK-B313BHK2291 of 1
BLOCK-B312BHK1292 of 2
BLOCK-B313BHK2121 of 1
BLOCK-B324BHK3322 of 2
BLOCK-B323BHK1952 of 2
BLOCK-B323BHK2291 of 1
BLOCK-B323BHK2121 of 1
BLOCK-B322BHK1292 of 2

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

BRICKS RAMABHUPAL PROJECTS LLP

LLPPromoter type
Ranga Reddy, TelanganaBased in
1Projects
1City
2022–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
TELLAPUR
Village
TELAPUR
Mandal
RC PURAM
District
Sangareddy
Pincode
502032
North boundary
Aakriti arv viva villas
East boundary
BUND
South boundary
Mega Meadows
West boundary
100 FEET ROAD
What’s nearby
SchoolsNearest school 1.2km away · College or university 1.9km away · Kindergarten within 500m
HealthcareNearest hospital 2.7km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 4.8 kmPrimary road 3.2 km · Nallagandla FlyoverRailway line 1.2 kmRailway station 1.3km away (Telapur)Limited bus connectivity nearby
Water & environment
Water body 377 m
distances only — not a flood assessment
Government land classification

No residential (House Sites) class on record. The state classes this village’s land as Dry land, Wet Land double crop. If it’s sold as residential plots, verify the layout’s conversion / approval.

Telangana Registration & Stamps
Declared external development
Roads0%
Water supply0%
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Hyderabad Metropolitan Development Authority (HMDA)

Urban Development Authority
Building Permit no. 047316/SKP/R1/U6/HMDA/17072021Survey no. 407/A1 AND 407/A2/1,2,3
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan 047316/SKP/R1/U6/HMDA/17072021 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

HMDA

Urban Development Authority · Hyderabad metropolitan periphery

Has approved 3,643 RERA projectsabout 1 in 3 in Telangana.

an apartments market72% apartments · 28% plotted layouts. Apartments like yours are this body's core business.

Builders
2,462
On record
3,98,695 flats · 1,96,015 plots
Reach
71 mandals
Since
2016

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.