Complete project overview

RAJ-RERA · Registration filing
Plots
98 plots
Land area
23,834 sq m
Completion deadline extended
1 extension on record — latest to 22 Apr 2026declared reason: other than force majeure
Description
The Land Owner presented an application before the District Collector, Alwar, for revision of its approved maps and the same were approved in the 10th meeting of the Layout Plan Approval Committee dated 21.10.2020 headed by the District Collector, Alwar.

Timeline

Construction startSep 2024
RERA registeredDec 2024
Proposed completionApr 2025
TodayJul 2026

Find your plot

Filed by type and size, in the batches the promoter registered — not a per-plot listing. Look yours up.

98 plots across 60 batches
TypeArea sq mCount
Plot831
Plot851
Plot7338
Plot351
Plot581
Plot831
Plot821
Plot351
Plot871
Plot751
Plot471
Plot671
Plot681
Plot831
Plot351
Plot721
Plot611
Plot811
Plot771
Plot471
Plot571
Plot621
Plot651
Plot791
Plot351
Plot591
Plot771
Plot631
Plot902
Plot671
Plot821
Plot661
Plot741
Plot471
Plot841
Plot671
Plot791
Plot471
Plot831
Plot831
Plot861
Plot781
Plot821
Plot681
Plot801
Plot581
Plot991
Plot811
Plot761
Plot691
Plot801
Plot791
Plot691
Plot351
Plot861
Plot681
Plot831
Plot631
Plot821
Plot781

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each size exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

RAJ-RERA · Promoter registration

Mgi Infratech Private Limited

OrganisationPromoter type
Alwar, RajasthanBased in
3Projects
1City
2017–2025Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
112 homes · 98 plotson the public record across 3 projects
7,708 sq mbuilt-up filed
47,668 sq mplotted area
71,502 sq mland declared
₹25.81 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
193, 191, 509/204, 510/205, Chawandi Khurd, Tijara, Alwar, 301411
Village
Chawandi Khurd
Taluka
Tijara
District
Alwar
Pincode
301411
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 2.7km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Primary road 122 mNo metro or railway within 5kmLimited bus connectivity nearby
Price analysisdeclared build cost — not a sale price

₹4.49 Cr declared to build 98 plots. What that works out to:

₹4.58 Lakhdeclared cost per plotall-in — land + construction
₹175/sq ftof plotted area₹1,882/sq m
55%of the cost is land₹96/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RAJ-RERA · Approved building plan
Layout Permitapproved 4 Dec 2024 · 1 yr ago

The promised possession date (22 Apr 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.