HORIZONMarkets
01

Complete project overview

RERA Karnataka · Registration filing
Status
New Project Launch
Units
36 units
Unit mix
24 × 3 BHK · 12 × 2 BHK
Towers
1
Floors
3
Land area
1,735 sq m
Built-up area
3,456 sq m
FAR sanctioned
1.75
Covered area
967 sq m
Open area
768 sq m
Land parcels
1 survey no

Timeline

Project startedMar 2026
RERA registeredMay 2026
Proposed completionDec 2028
TodayJul 2026

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

36 units across 2 batches
TypeArea sq mCount
2 BHK6812
3 BHK8524

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

RERA Karnataka · Promoter registration

MGR INFRA

Partnership FirmPromoter type
Bengaluru UrbanBased in
2Projects
2Cities
2025–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
36 homeson the public record across 2 projects
8,344 sq mbuilt-up filed
8,235 sq mland declared
₹18.75 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Hoskote Planning AuthorityTown & Country Planning (DTCP)this project1 of 2 projects
Talegaon Dabhade Municipal CouncilMunicipal Council1 of 2 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RERA Karnataka · Registration filing
Taluk
Bengaluru East
District
Bengaluru Urban
Pincode
560049
Address
Sy.No.100/1, situated at Manduru Village, Bidarahalli Hobli , Bengaluru East Taluk, Bengaluru , Bengaluru East , Bengaluru Urban, Karnataka - 560049
North boundary
La Sa No.102,
East boundary
La Hi No.2,
South boundary
La Hi No.3,
West boundary
Block-1,
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 4.4km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 3.6 kmPrimary road 460 m · Budigere RoadNo metro or railway within 5km2 bus stops within 500m
Water & environment
Water body 194 m
distances only — not a flood assessment
Land, title & encumbrance
LandJoint development (JDA) — built on the owner’s land by agreement
ConversionConverted to non-agricultural
LitigationDeclared free of litigation
BorrowingProject borrowing declared
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
Price analysisdeclared build cost — not a sale price

₹18.75 Cr declared to build 36 flats. What that works out to:

₹52.08 Lakhdeclared cost per flatall-in — land + construction
₹5,040/sq ftof built-up area₹54,253/sq m
2%of the cost is land₹214/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RERA Karnataka · Approved building plan

Hoskote Planning Authority

Town & Country Planning (DTCP)
approved 13 Oct 2025 · 9 mo ago
Building Permit no. CC/311/25-26Survey no. 100/1
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan CC/311/25-26 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

Hoskote Planning Authority

Town & Country Planning

Has approved 38 RERA projects0.4% of Karnataka.

a mixed market61% apartments · 39% plotted layouts.

Builders
36
On record
3,524 flats · 1,940 plots
Reach
2 taluks
Since
2025

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Complaints register

None on record with RERA Karnataka against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.