HORIZON
Share

MOHAN ENCLAVE

P-SGR-19-2317 · RERA Madhya Pradesh · https://gethorizon.in/projects/mohan-enclave-sagar-eeexywbh

01

Complete project overview

RERA Madhya Pradesh · Registration filing
Project name
MOHAN ENCLAVE
Plots
152 plots
Unit mix
14 × 4.57 X 15.24 Plot · 14 × 6.71 X 15.24 Plot · 12 × 4.27 X 8.67 Plot · 10 × 6.71 X 14.33 Plot · 8 × 5.00 X 10.67 Plot · 7 × Irreagulor Plot
Revised completion
30 Jul 2022extended after an approved RERA extension
Extensions
2 approved · Covid19completion-date extension(s) granted by RERA
Quarterly reports
8 on file · latest Oct 2018 - Dec 2018quarterly progress certificates filed with RERA

Timeline

Project startedNov 2018
RERA registeredAug 2019
Proposed completionOct 2021
TodaySep 2026

Find your plot

Filed by type and size, in the batches the builder registered — not a per-plot listing. Look yours up.

152 plots across 47 batches
TypeArea sq mCount
4.27 X 8.67 Plot12
5.00 X 10.67 Plot8
Irreagulor Plot7
5.38 X 10.67 Plot3
7.00 X 8.67 Plot2
7.83 X 8.67 Plot2
4.57 X 15.24 Plot14
5.08 X 14.33 Plot1
5.18 X 14.33 Plot5
5.49 X 14.00 Plot4
7.62 X 10.67 Plot1
6.71 X 12.76 Plot5
7.10 X 12.76 Plot1
6.40 X 14.33 Plot1
7.32 X 12.76 Plot2
6.71 X 14.00 Plot4
8.83 X 10.67 Plot1
6.71 X 14.33 Plot10
9.14 X10.67 Plot1
7.13 X 14.33 Plot1
6.71 X 15.24 Plot14
8.23 X 12.76 Plot1
6.71 X 15.85 Plot3
6.71 X 16.00 Plot4
7.10 X 15.24 Plot1
7.32 X 15.24 Plot2
8.12 X 14.00 Plot1
7.62 X 15.24 Plot6
9.11 X 12.76 Plot1
6.71 X 17.37 Plot2
9.14 X 12.76 Plot1
7.32 X 16.00 Plot3
8.23 X 14.33 Plot1
7.62 X 15.85 Plot2
8.23 X 15.24 Plot1
9.15 X 14.00 Plot1
8.12 X 16.00 Plot1
9.09 X 14.33 Plot2
7.62 X 17.37 Plot1
7.62 X 17.53 Plot3
9.11x 15.24 Plot1
9.14 X 15.24 Plot5
9.14 X 15.85 Plot1
9.15 X 16.00 Plot1
9.14 X 17.37 Plot1
9.14 X 19.81 Plot6
12.19 X 15.24 Plot1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each size exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

RERA Madhya Pradesh · Builder registration

KALPDHAM BUILDERS AND DEVELOPERS

Partnership Firm / LLPPromoter type
10Projects
3Cities
2019–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
1,088 plotson the public record across 10 projects
₹76.19 Crdeclared build cost

Build cost is what the builder declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
SagarTown & Country Planning (DTCP)this project9 of 10 projects
MandideepTown & Country Planning (DTCP)1 of 10 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from KALPDHAM BUILDERS AND DEVELOPERS— the full portfolio →

03

Location & price analysis

RERA Madhya Pradesh · Registration filing
District
Sagar
Tehsil
Sagar
Planning area
Sagar
Address
Khasra no. 217/2/1, 217/7, 219/2, 219/4, 219/5, 219/6, 219/7, Rajghat Road, Tilli Maafi, Baghraj Ward, Tehsil Sagar, District Sagar , PIN 470002
What’s nearby
SchoolsNearest school 1.6km away · 4 educational institutions within 1km · College or university 149m away
HealthcareHospital 76m away
LifestylePark 1.7km away · 3 restaurants and cafes within 1km
ShoppingSupermarket 1.6km away · Bank 52m away
Getting around
Expressway 4.3 kmPrimary road 66 mRailway line 4.6 km · Bina - Katni railwayRailway station 4.2km away (Saugor Railway Station P...... 2)Limited bus connectivity nearby
Water & environment
Water body 2.4 km
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹9.18 Cr declared to build 152 plots. What that works out to:

₹6.04 Lakhdeclared cost per plotall-in — land + construction
58%of the cost is land

This is what the builder filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Government Guidance Rate

MP Department of Registration & Stamps

In Madhya Pradesh it’s called the collector guideline rate.

₹15,050per sq yd
₹18,000per sq m
Which rate
open plot, residential
Matched to
The middle rate of the 105 colonies within 3 km of this project — its neighbourhood, not a single colony.
In force
2026-2027 schedule · effective Apr 2026

Colonies around this project

RAJGHAT TIRAHE SE DAYMAND PETROL PUMP HOTE HUYE KISHOR SAMPREKSHAN GRAH TAK ROAD PAR₹40,000 / sq m₹33,445 / sq yd180 m
SHIVBIHAR COLONY₹20,000 / sq m₹16,723 / sq yd220 m
Tilimafi Road Ke Andar₹12,000 / sq m₹10,034 / sq yd460 m
MADHUVAN LIFE STYLE CALONY / MADHUVAN ECO CITY CALONY₹20,000 / sq m₹16,723 / sq yd500 m
NAVNIRMAN BUILDERS MANSROVAR COLONY₹20,000 / sq m₹16,723 / sq yd500 m

The same schedule, published for the places around this one — so the figure above reads in its neighbourhood, not alone.

What this number is — and isn’t

  • The minimum value Madhya Pradesh’s registration department will register a sale at. Stamp duty is usually charged on this or the price in the sale deed, whichever is higher.
  • Not a market price. Sales normally register above it, and how far above varies by place and by project.
  • Its fit depends on the grain the state publishes at. This one is matched at the level of locality, and says so above. How Horizon decides what to show.
05

Planning authority

RERA Madhya Pradesh · Approved building plan

Sagar

Town & Country Planning (DTCP)
Layout Permit

The promised possession date (31 Oct 2021) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Sagar

Town & Country Planning area · Sagar district

Has approved 50 RERA projects0.9% of Madhya Pradesh.

a plotted-layout market12% apartments · 88% plotted layouts. Your plotted layout is this body's core business.

Builders
33
On record
728 flats · 3,896 plots
Reach
2 tehsils
Since
2017

More layout-heavy than Madhya Pradesh overall — 88% plots here vs 72% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by RERA Madhya Pradesh

07

Other projects nearby

The register · within 25 km

21 plotted projects still under way within 25 km. Step out ring by ring:

16 projects between 1 and 3 km — showing the nearest 6.

SagarPlotted Development

AACHARAN ECO CITY PHASE-III

KALPDHAM BUILDERS AND DEVELOPERS

Jun 2024registered
Oct 2026target completion
Declared cost₹7.03 CrScale59 plotsAuthorityRERA Madhya Pradesh
SagarPlotted Development

RADHA RAMAN ENCLAVE

RICHHARIYA BUILDERS AND DEVELOPERS

Aug 2024registered
Aug 2026target completion
Declared cost₹2.87 CrScale50 plotsAuthorityRERA Madhya Pradesh
SagarPlotted Development

PALM VALLEY

SUNIL JADIYA

Apr 2026registered
Oct 2028target completion
Declared cost₹3.57 CrScale31 plotsAuthorityRERA Madhya Pradesh
SagarPlotted Development

DHARAM SHREE COLONY

M.P.HOUSING BOARD DIVISION SAGAR

Oct 2025registered
May 2028target completion
Declared cost₹79.11 CrScale56 plotsAuthorityRERA Madhya Pradesh
SagarPlotted Development

UDAY RESIDENCY

KALPDHAM BUILDERS AND DEVELOPERS

Jun 2024registered
Sep 2026target completion
Declared cost₹5.27 CrScale58 plotsAuthorityRERA Madhya Pradesh
SagarPlotted Development

MOHAN ENCLAVE PHASE-II

KALPDHAM BUILDERS AND DEVELOPERS

Jun 2024registered
Oct 2026target completion
Declared cost₹16.98 CrScale76 plotsAuthorityRERA Madhya Pradesh

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. This project’s coordinate is approximate, so distances are rough.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Complaints — RERA Madhya Pradesh does not publish a complaints register. This read cannot speak to them either way.