Complete project overview

RAJ-RERA · Registration filing
Land area
48,833 sq m
Completion deadline extended
2 extensions on record — latest to 30 Aug 2021declared reason: force majeure
Description
It is a plotting project named MY WORLD located at Abu Road, Sirohi with provision of 173 plots having total area 45061.54 sq mtrs commenced on 15th June 2016 including common area of Internal Roads, Gardens & O.C.F. .Also the project is being developed in Phases and this is the current phase.The Estimated Finish date of the project was extended on 02-01-2020. This bears the approval of Honorable Chairman, before extension the estimated finish date was 27-12-2019

Timeline

Construction startJun 2016
RERA registeredSep 2017
Proposed completionAug 2020
TodayJul 2026
02

Builder’s track record

RAJ-RERA · Promoter registration

BG Mutha Group

OrganisationPromoter type
Sirohi, RajasthanBased in
1Projects
1City
2017–2020Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
382,778/383,747/388, Abu Road, VILLAGE MUDURLA, Abu Road, Sirohi, 307510
Village
VILLAGE MUDURLA
Taluka
Abu Road
District
Sirohi
Pincode
307510
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 3.8km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 844 m · Off rampRailway line 1.6 kmRailway station 2.1km away (Kivarli)Limited bus connectivity nearby
Water & environment
River 541 mWater body 3.5 km
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹3.38 Cr declared. What that works out to:

₹64/sq ftof plotted area₹692/sq m
16%of the cost is land₹10/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RAJ-RERA · Approved building plan

Gram Panchayat

Gram Panchayat
Layout Permitapproved 13 Sep 2017 · 8 yrs ago

The promised possession date (30 Aug 2020) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Gram Panchayat

A village-level local body. It has approved 34 RERA projects across 5 districts 1.5% of Rajasthan.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.