HORIZONMarkets
01

Complete project overview

WBRERA · Registration filing
Apartments
27
Land area
5,091 sq m
Built-up area
13,348 sq m
Carpet area
10,515 sq m
Parking
170 spaces
RERA registered
2024

Timeline

RERA registeredJan 2024
Proposed completionDec 2029
TodayJul 2026
02

Builder’s track record

WBRERA · Promoter registration

Arrjavv Builder Private Limited

Company / LLPPromoter type
Kolkata, West BengalBased in
1Projects
1City
2024–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

WBRERA · Registration filing
District
Kolkata
Police station
Karaya
Address
Premises No. 2 Bright Street
Pincode
700019
What’s nearby
Schools4 schools within 1km · 4 educational institutions within 1km · College or university 1.0km away
HealthcareHospital 314m away · 6 clinics within 1km · Pharmacy within 500m
LifestylePark 1.6km away · Gym or sports centre 1.2km away · 17+ restaurants and cafes within 1km
ShoppingSupermarket 424m away · Mall 167m away · Bank 131m away
Getting around
Expressway 642 m · Maa FlyoverPrimary road 133 m · Syed Amir Ali AvenueRailway line 744 m · Kolkata Circular RailwayRailway station 996m away (Park Circus)Bus stop within 500m
Water & environment
Water body 289 m
distances only — not a flood assessment
04

Planning authority

WBRERA · Approved building plan

Kolkata Municipal Corporation

Municipal Corporation
Building Permit
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Kolkata Municipal Corporation

Municipal corporation / municipality

Has approved 1,030 RERA projectsabout 1 in 2 in West Bengal, more than any other body in the state.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
776
On record
14,568 flats · 0 plots
Reach
5 districts

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — WBRERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — WBRERA does not publish a complaints register. This read cannot speak to them either way.
  • Escrow — WBRERA does not publish escrow declarations. Whether buyer money is ring-fenced cannot be read here.