Complete project overview

RERA Telangana · Registration filing
Units
50 units
Unit mix
35 × 2BHK, 15 × 3BHK
Saleable area
96–126 sq mper unit, as filed
Floors
5
Land area
3,700 sq m
Built-up area
4,931 sq m

Timeline

RERA approvedMar 2018
Proposed completionSep 2021
TodayJul 2026
Construction progress

39.5% overall, as filed

Podiums0%
OC-readiness5%
Flat fit-out10%
External finishes10%
Stairs & lifts25%
Internal finishes40%
Superstructure45%
Stilt floor60%
Excavation100%
Basement & plinth100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

44 of 50 available
BuildingFloorTypeArea sq mAvailable
NATURENEST12BHKmortgaged971 of 1
NATURENEST12BHKmortgaged961 of 1
NATURENEST12BHK961 of 1
NATURENEST12BHK981 of 1
NATURENEST12BHK1001 of 1
NATURENEST12BHK1031 of 1
NATURENEST13BHKmortgaged1241 of 1
NATURENEST13BHKmortgaged1262 of 2
NATURENEST12BHKmortgaged971 of 1
NATURENEST22BHK971 of 1
NATURENEST22BHK962 of 2
NATURENEST22BHK981 of 1
NATURENEST22BHK1001 of 1
NATURENEST22BHK1031 of 1
NATURENEST23BHK1241 of 1
NATURENEST23BHK1262 of 2
NATURENEST22BHK970 of 1
NATURENEST32BHK971 of 1
NATURENEST32BHK961 of 2
NATURENEST32BHK981 of 1
NATURENEST32BHK1001 of 1
NATURENEST32BHK1031 of 1
NATURENEST33BHK1241 of 1
NATURENEST33BHK1261 of 2
NATURENEST32BHK971 of 1
NATURENEST42BHK962 of 2
NATURENEST42BHK981 of 1
NATURENEST42BHK1001 of 1
NATURENEST43BHK1241 of 1
NATURENEST43BHK1262 of 2
NATURENEST42BHK971 of 1
NATURENEST42BHK1030 of 1
NATURENEST42BHK970 of 1
NATURENEST52BHK971 of 1
NATURENEST52BHK962 of 2
NATURENEST52BHK981 of 1
NATURENEST52BHK1001 of 1
NATURENEST52BHK1031 of 1
NATURENEST53BHK1241 of 1
NATURENEST53BHK1261 of 2
NATURENEST52BHK971 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

SRI VC AND GG BUILDERS

PartnershipPromoter type
Medchal-Malkajgiri, TelanganaBased in
1Projects
1City
2018–2021Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
ETDC
Mandal
Kapra
District
Medchal-Malkajgiri
Pincode
500062
North boundary
NEIGHBOURS LAND
East boundary
OPEN JAIL
South boundary
LAND BELONGS TO M SARASWATHI AND OTHERS
West boundary
30 FEET WIDE ROAD
What’s nearby
Schools1 school within 1km
HealthcareHospital 285m away · 1 clinic within 1km · Pharmacy within 1km
LifestyleNo parks within 2km · Gym or sports centre 468m away · 39+ restaurants and cafes within 1km
ShoppingSupermarket 345m away · Mall 348m away · Bank 171m away
Getting around
Primary road 633 m · ECIL JunctionRailway line 2.8 kmRailway station 3.2km away (Neredmet)2 bus stops within 500m
Water & environment
Water body 842 m
distances only — not a flood assessment
Declared external development
Water supply25%
Electricity10%
Roads0%
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Greater Hyderabad Municipal Corporation (GHMC)

Municipal / Corporation
Building Permit no. 1/C1/04798/2018Survey no. 218&219

The promised possession date (18 Sep 2021) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan 1/C1/04798/2018 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

GHMC

Municipal Corporation · Hyderabad city core

Has approved 3,102 RERA projectsabout 1 in 4 in Telangana.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,994
On record
2,20,211 flats · 3,387 plots
Reach
65 mandals
Since
2016

More apartment-heavy than Telangana overall — 99% apartments here vs 66% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.