Complete project overview

RERA Telangana · Registration filing
Units
10 units
Unit mix
5 × 3BHK, 5 × 2BHK
Saleable area
97–117 sq mper unit, as filed
Floors
5
Land area
334 sq m
Built-up area
1,738 sq m

Timeline

RERA approvedJun 2021
Proposed completionJun 2026
TodayJul 2026
Construction progress

60% overall, as filed

Basement & plinth0%
Podiums0%
Flat fit-out20%
Stairs & lifts50%
OC-readiness60%
Internal finishes80%
External finishes90%
Excavation100%
Stilt floor100%
Superstructure100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

10 of 10 available
BuildingFloorTypeArea sq mAvailable
NC JASMIN RESIDENCY13BHK1171 of 1
NC JASMIN RESIDENCY12BHK971 of 1
NC JASMIN RESIDENCY23BHKmortgaged1171 of 1
NC JASMIN RESIDENCY22BHK971 of 1
NC JASMIN RESIDENCY33BHK1171 of 1
NC JASMIN RESIDENCY32BHK971 of 1
NC JASMIN RESIDENCY43BHK1171 of 1
NC JASMIN RESIDENCY42BHK971 of 1
NC JASMIN RESIDENCY53BHKmortgaged1171 of 1
NC JASMIN RESIDENCY52BHK971 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

NITHIN CONSTRUCTIONS

PartnershipPromoter type
Ranga Reddy, TelanganaBased in
5Projects
3Cities
2018–2026Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
140 homeson the public record across 5 projects
15,731 sq mbuilt-up filed
5,654 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Hyderabad Metropolitan Development Authority (HMDA)Urban Development Authoritythis project3 of 5 projects
Directorate of Town & Country Planning (DTCP)Town & Country Planning (DTCP)1 of 5 projects
Greater Hyderabad Municipal Corporation (GHMC)Municipal / Corporation1 of 5 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
AMEENPUR
Village
AMEENAPUR
Mandal
AMEENPUR
District
Sangareddy
Pincode
502302
North boundary
NEIGHBOURS LAND
East boundary
PLOT NO 199
South boundary
PLOT NO 201
West boundary
ROAD WIDTH 12
What’s nearby
SchoolsNo schools within 2km
HealthcareNo hospital within 5km · Clinic within 2km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Primary road 538 mNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
Water body 2.1 km · Chinna CheruvuRiver 4.2 km · Manjira
distances only — not a flood assessment
Government land classification

No residential (House Sites) class on record. The state classes this village’s land as Dry land, Wet Land double crop. If it’s sold as residential plots, verify the layout’s conversion / approval.

Telangana Registration & Stamps
Declared external development
Water supply90%
Roads0%
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Hyderabad Metropolitan Development Authority (HMDA)

Urban Development Authority
Building Permit no. 042286/SKP/R1/U6/HMDSurvey no. 109

The promised possession date (2 Jun 2026) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan 042286/SKP/R1/U6/HMD on the approving authority’s portal to confirm the sanction.

The approving body, at scale

HMDA

Urban Development Authority · Hyderabad metropolitan periphery

Has approved 3,643 RERA projectsabout 1 in 3 in Telangana.

an apartments market72% apartments · 28% plotted layouts. Apartments like yours are this body's core business.

Builders
2,462
On record
3,98,695 flats · 1,96,015 plots
Reach
71 mandals
Since
2016

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.