Complete project overview

RERA Karnataka · Registration filing
Status
Completed
Land area
38,343 sq m
Covered area
21,085 sq m
Open area
17,258 sq m

Timeline

Project startedMay 2015
RERA registeredOct 2017
Proposed completionNov 2019
TodayJul 2026
02

Builder’s track record

RERA Karnataka · Promoter registration

NCC URBAN INFRASTRUCTURE LTD

Bengaluru UrbanBased in
6Projects
2Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
6 projectson the public record across 6 projects
1,29,903 sq mplotted area
1,45,346 sq mland declared
₹267.83 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
CMDA (Chennai Metropolitan Development Authority)CMDA (Chennai Metropolitan Development Authority)3 of 6 projects
BBMP - Bruhat Bengaluru Mahanagara PalikeMunicipal / Corporation1 of 6 projects
BDA - Bangalore Development AuthorityUrban Development Authoritythis project1 of 6 projects
BMRDA - Bangalore Metropolitan Region Development AuthorityUrban Development Authority1 of 6 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RERA Karnataka · Registration filing
Taluk
Bengaluru North
District
Bengaluru Urban
Pincode
560034
Address
NCC URBAN MISTY WOODS, VADERAPURA VILLAGE, YELAHANKA HOBLII, BENGALURU-560064, NCC URBAN MISTY WOODS, VADERAPURA VILLAGE, YELAHANKA HOBLII, BENGALURU-560064
What’s nearby
SchoolsNo schools within 2km · College or university 1.5km away · Library 1.7km away
HealthcareHospital 229m away · 2 clinics within 1km
LifestyleNo parks within 2km · 3 restaurants and cafes within 1km
ShoppingSupermarket 1.5km away
Getting around
Expressway 362 m · Bellary RoadPrimary road 2.6 kmRailway line 2.2 kmRailway station 2.4km away (Yelahanka Junction)4 bus stops within 500m
Water & environment
Water body 530 m
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹80.00 Cr declared. What that works out to:

₹1,938/sq ftof plotted area₹20,864/sq m
0%of the cost is land₹0/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RERA Karnataka · Approved building plan

BDA - Bangalore Development Authority

Urban Development Authority
Layout Permit

The promised possession date (29 Nov 2019) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

BDA

Urban Development Authority · Bangalore Development Authority

Has approved 830 RERA projectsabout 1 in 11 in Karnataka.

an apartments market73% apartments · 27% plotted layouts. Layouts like yours are the smaller share here — this body mostly approves apartments.

Builders
626
On record
82,843 flats · 16,515 plots
Reach
13 taluks
Since
2017

More apartment-heavy than Karnataka overall — 73% apartments here vs 62% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Complaints register

None on record with RERA Karnataka against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.