Complete project overview

GujRERA · Registration filing
Units
150 units
Mix
140 × Residential · 10 × Commercial
Carpet area
11–96 sq mper-unit range, as filed
Blocks
4
Parking
160 spaces
Land area
5,285 sq m

Timeline

Project startedApr 2019
RERA registeredJun 2020
Proposed completionJun 2024
TodayJul 2026
Construction progress

100% overall, as filed

Overall % complete as filed with GujRERA, taken as the slowest of the project's blocks — a snapshot, not a live tracker. Where a BU permission is on record (section 04), that is the firmer completion signal.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

150 units across 2 batches
TypeArea sq mCount
Residential75140
Commercial2310

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

GujRERA · Promoter registration

R. K. DEVELOPERS

PARTNERSHIP FIRMPromoter type
Gandhinagar, GujaratBased in
16Projects
13Cities
2018–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
268 homes · 1,236 plotson the public record across 16 projects
18,440 sq mbuilt-up filed
59,755 sq mplotted area
69,552 sq mland declared
₹198.82 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Anekal Planning AuthorityTown & Country Planning (DTCP)2 of 9 projects
Directorate of Town & Country Planning (DTCP)Town & Country Planning (DTCP)2 of 9 projects
Director, Town and Country PlanningTown & Country Planning (DTCP)1 of 9 projects
Gandhinagar Urban Development AuthorityUrban Development Authoritythis project1 of 9 projects
Local Planning AuthorityTown & Country Planning (DTCP)1 of 9 projects
Municipal Corporation of Greater MumbaiMunicipal Corporation1 of 9 projects
UjjainTown & Country Planning (DTCP)1 of 9 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

GujRERA · Registration filing
Taluka
Gandhinagar
District
Gandhinagar
Address
NEAR AKSHAR VILLA & KUNJ HEIGHTSVAVOL - UVARSAD ROAD, VAVOL
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 2.0km away · 1 clinic within 1km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 2.9 kmPrimary road 1.0 kmRailway line 857 mRailway station 2.4km away (Gandhinagar Capital)Limited bus connectivity nearby
Water & environment
Water body 1.2 km · Vavol Lake
distances only — not a flood assessment
Land, title & encumbrance
MortgageLoan outstanding · ₹20.9 Lakh outstanding
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
Price analysisdeclared build cost — not a sale price

₹28.92 Cr declared to build 150 flats. What that works out to:

₹4.70 Lakh – ₹40.00 Lakhdeclared unit pricerange on the filing — not a live asking price
₹19.28 Lakhdeclared cost per flatall-in — land + construction
₹2,522/sq ftof carpet area₹27,142/sq m
13%of the cost is land₹646/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

GujRERA · Approved building plan

Gandhinagar Urban Development Authority

Urban Development Authority
Building Permitapproved 3 Jun 2020 · 6 yrs ago

The promised possession date (30 Jun 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

Building-Use (BU) permission — the occupancy sign-off, on record

All 4 blocks carry a Building-Use (BU) permission (latest 18 Mar 2023)— Gujarat’s legal-to-occupy sign-off, and the completion proof most RERA records simply don’t carry. Still confirm the BU covers your specific unit before you rely on it.

The approving body, at scale

Gandhinagar Urban Development Authority

Urban Development Authority

Has approved 414 RERA projects2.4% of Gujarat.

an apartments market95% apartments · 5% plotted layouts. Apartments like yours are this body's core business.

Builders
355
On record
47,140 flats · 710 plots
Reach
5 talukas
Since
2010

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Complaints — GujRERA does not publish a complaints register. This read cannot speak to them either way.