Complete project overview

RAJ-RERA · Registration filing
Land area
7,838 sq m
Completion deadline extended
2 extensions on record — latest to 31 Dec 2021declared reason: force majeure
Description
As per applicant request application for seeking extension in estimated finish date and further to the approval of hon'ble Chairman on dated 17.02.2020, estimated finish date has been changed from 31.12.2019 to 31.12.2020. Therefore now estimated finish date should be read as 31.12.2020.Estimated finished date updated on 19-02-2020. The Promoter shall obtain from the competent authority the requisite extension of validity of approved building plans and submit a copy thereof to the authority latest by 31.07.2020, failing which this certificate of extension shall stand withdrawn.

Timeline

Construction startJun 2010
RERA registeredDec 2017
Proposed completionDec 2020
TodayJul 2026
02

Builder’s track record

RAJ-RERA · Promoter registration

Unique Developers Pvt Ltd

OrganisationPromoter type
Jaipur, RajasthanBased in
1Projects
1City
2017–2020Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
GH-6, Diggi Malpura , Ratalya, Sanganer, Jaipur, 302029
Village
Ratalya
Taluka
Sanganer
District
Jaipur
Pincode
302029
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 1.5km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Primary road 1.4 km · Diggi Malpura RdNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
Canal 4.5 km
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹22.36 Cr declared. What that works out to:

28%of the cost is land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RAJ-RERA · Approved building plan

Jaipur Development Authority

Development Authority
Building Permitapproved 28 Dec 2017 · 8 yrs ago

The promised possession date (31 Dec 2020) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Jaipur Development Authority

Development authority

Has approved 644 RERA projectsabout 1 in 3 in Rajasthan, more than any other body in the state.

a mixed market52% apartments · 48% plotted layouts.

Builders
528
On record
15,937 flats · 30,970 plots
Reach
2 districts
Since
2017

More apartment-heavy than Rajasthan overall — 52% apartments here vs 34% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.